  "name": "Construction manager at risk (CMAR) delivery stages and the sources that describe them",
  "description": "Compares the stages of a CMAR / CM/GC delivery (pre-construction services, price agreement, early GMP, construction under the GMP, risk allocation, payment rules) as stated in FHWA guidance, 23 CFR 635, a CMAA-republished MBP article and one county sample contract.",
  "page": "https://casrai.org/guides/construction-manager-at-risk",
  "publisher": "CASRAI",
  "license": "https://creativecommons.org/licenses/by/4.0/",
  "dateModified": "2026-11-25T12:20:00Z",
  "temporalCoverage": "2026",
  "spatialCoverage": "United States",
  "columns": [
    {
      "name": "Stage",
      "unit": "",
      "description": ""
    },
    {
      "name": "What the source states",
      "unit": "",
      "description": ""
    },
    {
      "name": "Source",
      "unit": "",
      "description": ""
    },
    {
      "name": "Scope of source",
      "unit": "",
      "description": ""
    }
  ],
  "rows": [
    {
      "Stage": "Pre-construction services",
      "What the source states": "Contractor acts as consultant during design and offers constructability and pricing feedback on design options",
      "Source": "FHWA Every Day Counts, CM/GC",
      "Scope of source": "Highway CM/GC"
    },
    {
      "Stage": "Pre-construction services",
      "What the source states": "Consulting that gives the contracting agency and its designer information about the impacts of design",
      "Source": "23 CFR 635.502",
      "Scope of source": "Federal-aid highway"
    },
    {
      "Stage": "Pre-construction services",
      "What the source states": "Construction manager develops schedules, cost models and estimates, and value engineering as a member of the project team",
      "Source": "Loudoun County sample CM at Risk contract, Part 1",
      "Scope of source": "One county contract"
    },
    {
      "Stage": "Price agreement",
      "What the source states": "If owner, designer and independent cost estimator agree the price is fair, owner issues a construction contract",
      "Source": "FHWA Every Day Counts, CM/GC",
      "Scope of source": "Highway CM/GC"
    },
    {
      "Stage": "Price agreement",
      "What the source states": "If the agency is unwilling or unable to contract with the CM/GC contractor it may start a new procurement with Division Administrator concurrence",
      "Source": "23 CFR 635.504(b)(6)",
      "Scope of source": "Federal-aid highway"
    },
    {
      "Stage": "Price agreement",
      "What the source states": "GMP submitted at 100% completion of construction documents or a designated portion; includes construction phase fee, general conditions cost and allowances",
      "Source": "Loudoun County sample CM at Risk contract, Part 1",
      "Scope of source": "One county contract"
    },
    {
      "Stage": "Early GMP",
      "What the source states": "Early GMP may cover site work and long-lead major mechanical and electrical equipment",
      "Source": "Loudoun County sample CM at Risk contract, Part 1",
      "Scope of source": "One county contract"
    },
    {
      "Stage": "Construction under the GMP",
      "What the source states": "Construction manager is accountable for delivering the project within the GMP",
      "Source": "CMAA republication of MBP article",
      "Scope of source": "General description"
    },
    {
      "Stage": "Risk allocation",
      "What the source states": "Construction manager absorbs overrun if GMP set before trade buyout or full design; owner bears post-GMP design changes and design-progression gaps",
      "Source": "CMAA republication of MBP article",
      "Scope of source": "General description"
    },
    {
      "Stage": "Payment method",
      "What the source states": "Cost plus a percentage of cost and percentage of construction cost methods shall not be used; actual-cost compensation needs an approved indirect cost rate",
      "Source": "23 CFR 635.504(e)",
      "Scope of source": "Federal-aid highway"
    },
    {
      "Stage": "Contingency",
      "What the source states": "Design contingency decreases as construction documents become more complete; construction manager contingency sits within the GMP",
      "Source": "Loudoun County sample CM at Risk contract, Part 1",
      "Scope of source": "One county contract"
    }
  ],
  "sources": [
    {
      "title": "FHWA Every Day Counts: Construction Manager/General Contractor",
      "url": "https://www.fhwa.dot.gov/innovation/everydaycounts/edc-2/cmgc.cfm",
      "accessed": "2026-11-12"
    },
    {
      "title": "23 CFR 635.502 Definitions",
      "url": "https://www.law.cornell.edu/cfr/text/23/635.502",
      "accessed": "2026-11-12"
    },
    {
      "title": "23 CFR 635.504 CM/GC project requirements",
      "url": "https://www.law.cornell.edu/cfr/text/23/635.504",
      "accessed": "2026-11-12"
    },
    {
      "title": "Construction Management at-Risk: Who Is Really at Risk? (CMAA republication of MBP article)",
      "url": "https://www.cmaanet.org/sites/default/files/resource/CM%20At-Risk.pdf",
      "accessed": "2026-11-12"
    },
    {
      "title": "Loudoun County sample Construction Manager at Risk contract, Part 1 Pre-Construction Phase",
      "url": "https://www.loudoun.gov/DocumentCenter/View/213646",
      "accessed": "2026-11-12"
    }
  ]
}