Under the Uniform Guidance (2 CFR Part 200), section 2 CFR 200.308 governs the revision of budget and program plans for federal grants and cooperative agreements. It establishes the binding federal rules under which recipients must obtain prior written approval from the awarding agency before implementing significant programmatic alterations—such as changes in scope, key personnel substitutions, or principal investigator effort reductions exceeding 25 percent—or transferring funds out of restricted categories like participant support costs, while delineating the expanded authorities that permit routine rebudgeting and one-time no-cost extensions.
Administered across the executive branch under the regulatory authority of the Office of Management and Budget (OMB), 2 CFR 200.308 balances federal financial accountability with operational flexibility for research institutions. The regulation dictates how non-federal entities navigate budget deviations, establish internal reallocations, and maintain compliance throughout the post-award lifecycle, forming a central component of the Uniform Guidance (2 CFR 200) framework.
What it is and who runs it
Section 200.308 of Title 2 of the Code of Federal Regulations is titled ‘Revision of budget and program plans’ and resides within Subpart D (Post Federal Award Requirements). The regulation acts as the government-wide statutory standard defining when a grant recipient has the unilateral authority to adjust its expenditure plan and when it must formally request permission from the federal government. The overarching policy framework is established and maintained by the Office of Management and Budget (OMB) within the Executive Office of the President, in coordination with the Council on Financial Assistance Reform (COFAR).
While OMB establishes the baseline regulation in 2 CFR 200.308, execution and operational enforcement are delegated to individual federal awarding agencies. Major research funding bodies—including the National Institutes of Health (NIH), the National Science Foundation (NSF), the Department of Energy (DOE), and the Department of Defense (DOD)—implement 2 CFR 200.308 through agency-specific codifications and policy manuals. For example, the Department of Health and Human Services (HHS) adopts the Uniform Guidance under 45 CFR Part 75 and enforces specific rebudgeting thresholds in the NIH Grants Policy Statement (GPS), whereas NSF operationalizes the rule through Chapter X of its Proposal and Award Policies and Procedures Guide (PAPPG).
On April 22, 2024, OMB published a comprehensive overhaul of the Uniform Guidance (89 FR 30046), effective for awards issued on or after October 1, 2024. The 2024 revisions introduced meaningful structural changes to 2 CFR 200.308. Crucially, paragraph 200.308(e) reaffirmed that federal agencies cannot impose additional prior approval requirements beyond the codified guidance without explicit OMB approval. Furthermore, paragraph 200.308(f)(6) was revised to clarify that agency prior approval is not required simply to change a subrecipient unless the original subrecipient was a determining factor in the competitive merit review or eligibility process. Paragraph 200.308(d) was also reinforced to require federal agencies to review budget revision requests and render a decision within 30 days of receipt, or notify the recipient in writing when a determination will be made.
Eligibility (summary, with the official source)
As codified in 2 CFR 200.101 (Applicability) and detailed on the official eCFR portal, 2 CFR 200.308 applies to all non-federal entities that receive federal financial assistance awards in the form of grants or cooperative agreements. Eligible recipient classes encompass higher education institutions (universities and colleges), nonprofit research organizations, hospitals, state and local government agencies, and Indian tribal governments. When a recipient issues a subaward to carry out part of the federal program, the pass-through entity must flow down the provisions of 2 CFR 200.308 to the subrecipient, meaning subrecipients must seek prior approval from the pass-through entity rather than directly from the federal awarding agency.
The regulation draws an essential statutory distinction between research awards and non-research awards. Under 2 CFR 200.308(h), prior approval requirements for administrative waivers—such as 90-day pre-award spending, one-time no-cost extensions, and carryover of unobligated balances—are automatically waived for federal awards supporting research, unless an agency explicitly reserves prior approval in its published regulations or notice of award. This research-specific exemption underpins the ‘Expanded Authorities’ widely utilized by academic institutions.
Conversely, 2 CFR 200.308 does not apply to federal procurement contracts governed by the Federal Acquisition Regulation (FAR), direct federal assistance to individuals (such as personal fellowships, unless specifically conditioned), or fixed-amount awards under 2 CFR 200.201(b). Under fixed-amount awards, accountability is tied to the achievement of measurable performance milestones and deliverables rather than actual line-item costs incurred, relieving the recipient from routine budget modification approvals provided the underlying project scope remains unchanged.
What it funds or requires
Rather than funding a specific project, 2 CFR 200.308 mandates a compliance framework that governs how award funds are managed across budget categories. Under 2 CFR 200.308(a), the ‘approved budget’ represents the complete financial architecture sanctioned by the federal government, encompassing both the federal contribution and any agreed non-federal cost sharing. Recipients are obligated under paragraph 200.308(b) to monitor and report financial deviations and request formal approval whenever an intended change triggers one of the ten statutory categories outlined in 2 CFR 200.308(f).
The Ten Codified Prior Approval Triggers
Federal regulations stipulate that recipients must obtain prior written approval from the awarding agency for the following specific actions:
- Change in scope or objective (200.308(f)(1)): Any fundamental modification in the direction, aims, or methodology of the project, regardless of whether a financial budget adjustment is required.
- Change in key personnel (200.308(f)(2)): The replacement, addition, or removal of key personnel specifically named in the notice of award or approved application.
- Disengagement or effort reduction of the PI (200.308(f)(3)): The disengagement from the project for more than three continuous months, or a 25 percent reduction in time and effort devoted to the award over the course of the period of performance, by the approved project director or principal investigator.
- Subpart E cost items (200.308(f)(4)): Incurring expenditure items that independently require prior approval under 2 CFR 200 Subpart E (Cost Principles), such as capital expenditures, equipment acquisitions over threshold limits, or pre-award costs exceeding standard windows.
- Transfer of participant support costs (200.308(f)(5)): Any transfer of funds budgeted for participant support costs (stipends, subsistence, travel allowances) into other direct cost categories.
- Unapproved subawards (200.308(f)(6)): Issuing subawards, transferring, or contracting out programmatic activities that were not proposed in the approved application and award budget.
- Changes in cost-sharing (200.308(f)(7)): Any reduction or material modification in the approved non-federal cost-sharing or matching commitment.
- Need for additional federal funds (200.308(f)(8)): Any situation where completion of the project requires supplemental federal obligations, which requires federal agency review to prevent Antideficiency Act violations.
- Transfer between construction and non-construction (200.308(f)(9)): Reallocating funds between construction and operational non-construction budget line items.
- Discretionary no-cost extensions (200.308(f)(10)): Extending the period of performance beyond the initial one-time 12-month administrative waiver, or any extension that requires additional funds or changes project scope.
Expanded Authorities and Agency Waivers
Under 2 CFR 200.308(g), federal agencies possess the authority to waive certain prior approval requirements, effectively delegating administrative discretion to grantee institutions. Under 2 CFR 200.308(h), these waivers are automatically extended to federal research awards unless restricted by program terms. These flexibilities, termed Expanded Authorities, include:
- Pre-award costs (200.308(g)(1)): Recipients may incur allowable project expenses up to 90 calendar days prior to the effective date of the award. Such costs are incurred entirely at the recipient’s financial risk and must be charged to the initial budget period.
- One-time 12-month no-cost extension (200.308(g)(2)): Grantees may initiate a single extension of the performance period by up to 12 months without prior agency approval. The recipient must notify the federal agency in writing with supporting justification at least 10 calendar days prior to the expiration date. Crucially, the regulation forbids exercising this extension merely to expend remaining unobligated balances.
- Carryover of unobligated balances (200.308(g)(3)): Grantees may automatically carry forward unexpended funds from one budget period to subsequent budget periods, ensuring scientific continuity without annual agency re-authorization.
The 10 Percent Rebudgeting Restriction Rule
Under 2 CFR 200.308(i), federal agencies have the regulatory option to restrict direct cost transfers among categories (such as moving funds between personnel, travel, and supplies) when two conditions coincide: the total federal award value exceeds the simplified acquisition threshold, and the cumulative transfer amount exceeds or is expected to exceed 10 percent of the total approved budget (including cost-sharing). Where an agency exercises this clause in the award agreement, institutions must monitor cumulative transfers across all direct categories to avoid crossing the 10 percent threshold without written approval.
Application or compliance steps
Navigating budget and program revisions requires a disciplined institutional process. Research administrators, principal investigators, and departmental managers must execute five sequential compliance steps to ensure that requests are valid, timely, and compliant with both 2 CFR 200.308 and agency-specific requirements.
Step 1: Identify the operational trigger and determine authority. The project director and departmental administrator must assess the planned change against 2 CFR 200.308(f). If the reallocation involves ordinary line-item adjustments (such as shifting $15,000 from laboratory supplies to domestic travel to present findings at a symposium) and the award carries expanded authorities, the institution can approve the rebudget internally. However, if the modification involves PI effort reduction exceeding 25 percent, a change in scope, a new subaward, or a transfer out of participant support costs, formal prior approval is legally mandatory.
Step 2: Assemble the required justification and budget schedules. Under 2 CFR 200.308(c), budget revision requests must use the same budget format submitted in the original application unless an alternative format is authorized. The package must contain a clear programmatic justification explaining why the revision is necessary, how the change impacts the project’s specific aims, a line-item budget table detailing current and proposed allocations, and documentation confirming that reallocated costs comply with the cost principles of Subpart E.
Step 3: Institutional endorsement by the Authorized Organization Representative (AOR). Individual PIs do not have legal standing to bind the institution or contract directly with the federal government. The request must undergo rigorous review by the university or institutional Sponsored Projects Office (SPO). Once verified, the AOR formally signs and submits the request through the designated agency electronic portal (such as eRA Commons for NIH or Research.gov for NSF).
Step 4: Monitor the agency review timeline. Under 2 CFR 200.308(d), the federal awarding agency is obligated to review the request and notify the recipient of its determination within 30 calendar days of receipt. If an agency requires extended review time due to technical complexity, it must inform the recipient in writing with an expected decision date. Grantees must not obligate or expend funds under the proposed revision until written approval is issued.
Step 5: Record amendment and adjust general ledger accounts. Upon receiving written approval (typically conveyed via a revised Notice of Award or formal approval letter from the Grants Management Officer), sponsored programs accounting updates the institutional financial ledger, adjusts category budgets, and retains the approval documentation in the permanent award compliance file for single audit inspection.
Typical timeline phases (no calendar dates as facts)
Compliance under 2 CFR 200.308 spans the full lifecycle of a federal award. Because grant terms and agency timelines vary, institutions structure their compliance monitoring around distinct operational phases rather than fixed calendar dates.
Phase 1: Pre-Award and Award Initiation. Grantees evaluate initial project expenditures under 2 CFR 200.308(g)(1). Allowable costs incurred up to 90 calendar days prior to the effective start date are captured under pre-award authority. The approved budget is established in the institutional accounting system, locking in base allocations, cost-sharing commitments, and restricted categories.
Phase 2: Active Performance and Mid-Period Rebudgeting. As experimental or project work unfolds, financial managers track monthly expenditure trends against approved categories. Internal rebudgeting thresholds are tracked cumulatively. If unexpected programmatic needs arise—such as replacing essential instrumentation or adjusting technician effort—the project team determines whether the shift remains within institutional expanded authorities or requires external agency submission.
Phase 3: Scope and Key Personnel Realignment. When a PI anticipates an extended leave, sabbatical, or significant reduction in effort (surpassing 25 percent), or when collaborative subawards must be established, prior approval requests must be prepared at least 30 to 45 calendar days before the anticipated event to allow adequate time for agency review under the 30-day standard of 2 CFR 200.308(d).
Phase 4: Award Conclusion and Closeout Preparation. Approaching the end of the period of performance, the recipient assesses whether programmatic aims have been fully met. If additional time is required to conclude research without additional federal funds, the grantee initiates a one-time 12-month no-cost extension under 2 CFR 200.308(g)(2), submitting written notification to the federal agency at least 10 calendar days before the project expiration date. This choice must be distinguished from a competitive renewal, as explored in the comparison of a grant renewal versus no-cost extension.
Phase 5: Post-Award Audit and Closeout Reconciliation. During the final 120-day closeout window, final financial reports (SF-425) are reconciled against the general ledger. Single auditors review all rebudgeting transactions against 2 CFR 200.308 compliance files to confirm that all restricted cost shifts possessed timely prior written authorizations.
Common mistakes
Failure to adhere to 2 CFR 200.308 is one of the most frequent sources of adverse findings in Single Audits under Uniform Guidance Subpart F. Understanding common pitfalls helps institutions protect both their funding and their regulatory standing.
- Rebudgeting participant support costs without agency sign-off: Under 2 CFR 200.308(f)(5) and 2 CFR 200.456, funds budgeted for participant support costs are strictly protected. If an educational workshop costs less than budgeted, institutions often mistakenly transfer the surplus into general supplies or equipment. Moving funds out of participant support costs without prior written approval is an unallowable cost that auditors will disallow and claw back.
- Misinterpreting the 25 percent effort reduction rule: Under 2 CFR 200.308(f)(3), prior approval is triggered by a 25 percent reduction in the effort devoted to the award by the approved PI or project director, calculated against the effort committed in the approved application. For example, if a PI committed 20 percent effort to a project, a reduction of 5 percentage points (reducing effort to 15 percent) constitutes a 25 percent reduction (5 / 20 = 25%) and requires prior approval. Many investigators incorrectly assume the 25 percent threshold applies to their total institutional salary rather than the project commitment.
- Failing to observe the 10-day notice requirement for no-cost extensions: Under 2 CFR 200.308(g)(2), a one-time no-cost extension requires written notification to the federal agency at least 10 calendar days prior to award expiration. Submitting notification on the final day of the award or after expiration invalidates the institutional waiver, requiring formal agency prior approval that the agency is not obligated to grant.
- Exercising no-cost extensions solely to exhaust unspent balances: The regulatory text of 2 CFR 200.308(g)(2) explicitly states that a one-time extension ‘may not be exercised for the sole purpose of using unobligated balances.’ Extensions must be justified by technical continuity, data analysis, or programmatic delays; financial burn rate is an invalid justification.
- Unapproved subawards and contractor reclassifications: Issuing a subaward to an external institution or commercial laboratory to perform a substantive portion of the scientific work without prior approval violates 2 CFR 200.308(f)(6), even if funds were already budgeted under a generic contractual line item.
- Ignoring cumulative direct cost transfer limits: For awards containing the 10 percent rebudgeting restriction under 2 CFR 200.308(i), financial teams often track individual line-item changes in isolation rather than monitoring the cumulative aggregate across budget periods, resulting in inadvertent compliance breaches.
Related programs
To understand the regulatory ecosystem of 2 CFR 200.308, research administrators must examine related sections of the Uniform Guidance and key agency policy manuals that govern cost principles, performance monitoring, and budget modifications. For practical administrative context, consult our detailed analysis of federal grant budget mechanics and prior approval.
The table below summarizes the core statutory and policy frameworks directly related to 2 CFR 200.308, detailing their primary regulatory focus and intersection with post-award budget management.
| Regulation or Program Framework | Governing Authority | Primary Subject Matter | Operational Relationship to 2 CFR 200.308 |
|---|---|---|---|
| 2 CFR 200.407 | Office of Management and Budget | Prior written approval (Subpart E) | Compiles the comprehensive list of direct cost items requiring prior approval referenced in 200.308(f)(4). |
| 2 CFR 200.329 | Office of Management and Budget | Monitoring and reporting program performance | Establishes the performance reporting framework used to document deviations requiring 200.308 budget revisions. |
| 2 CFR 200.456 | Office of Management and Budget | Participant support costs | Defines allowable participant costs that are legally shielded from unauthorized rebudgeting under 200.308(f)(5). |
| 2 CFR 200.458 | Office of Management and Budget | Pre-award costs | Provides the cost principles governing the 90-day pre-award spending authority authorized under 200.308(g)(1). |
| NIH Grants Policy Statement (GPS) Sec. 8.1 | National Institutes of Health | Changes in project and budget | Implements 2 CFR 200.308 for biomedical awards, codifying SNAP expanded authorities and prior approval triggers. |
| NSF PAPPG Chapter X | National Science Foundation | Grant administration and prior approvals | Operationalizes 200.308 for NSF grants, requiring Research.gov notifications for key personnel and scope revisions. |
| Research Terms and Conditions (RTC) | Federal Demonstration Partnership | Federal research award standard terms | Standardizes expanded authorities and prior approval matrices across participating research agencies. |
In addition to these statutory sections, the data table below compares prior approval and expanded authority implementations across major federal granting agencies.
Frequently asked questions
Does 2 CFR 200.308 require prior approval to move money between travel and supplies?
In most research awards, moving funds between standard direct cost categories such as travel and supplies does not require prior agency approval, provided the grant includes expanded authorities and the shift does not alter the project’s scope, affect key personnel, or breach the 10 percent cumulative rebudgeting restriction under 2 CFR 200.308(i). However, if an agency specifically restricts line-item transfers in the notice of award, prior approval is mandatory.
How is the 25 percent reduction in PI effort calculated under 2 CFR 200.308(f)(3)?
The 25 percent reduction threshold is calculated relative to the approved commitment in the grant award, not the investigator’s total institutional appointment. For example, if a principal investigator committed 40 percent of their professional effort to a federal project, a reduction of 10 percentage points (down to 30 percent effort) represents a 25 percent reduction of the approved commitment (10 / 40 = 25%) and legally requires prior written agency approval.
What happens if a federal agency does not respond to a budget revision request within 30 days?
Under 2 CFR 200.308(d), the federal awarding agency is required to review the request and notify the recipient within 30 calendar days of receipt. If an agency cannot complete its review within 30 days, it must inform the recipient in writing with an expected decision date. A lack of agency response does not constitute implied or constructive approval; grantees must not execute the revision until formal written authorization is granted.
Can grant funds be moved out of participant support costs if a conference costs less than expected?
No. Under 2 CFR 200.308(f)(5), transferring funds budgeted for participant support costs to other budget categories requires prior written approval from the federal awarding agency. Any unexpended participant support funds remaining after the event cannot be unilaterally redirected into personnel, equipment, or supplies without explicit agency authorization.
What is the difference between an agency-approved budget revision and institutional expanded authorities?
An agency-approved budget revision involves a formal written request submitted to and approved by the federal Grants Management Officer for triggers listed in 2 CFR 200.308(f). Expanded authorities, authorized under 2 CFR 200.308(g) and automatically applied to research awards under 2 CFR 200.308(h), represent statutory waivers where the federal government delegates prior approval authority directly to the grantee institution for actions such as 90-day pre-award spending and one-time 12-month extensions.
Can a grantee request a second no-cost extension under 2 CFR 200.308?
Yes, but a second no-cost extension requires formal prior written approval from the federal awarding agency. While 2 CFR 200.308(g)(2) permits a recipient to exercise a single one-time extension of up to 12 months under institutional authority, paragraph 200.308(f)(10) specifies that any subsequent no-cost extension must be submitted to the agency for approval at least 10 calendar days prior to the revised conclusion of the period of performance.
Sources
- Electronic Code of Federal Regulations (eCFR), 2 CFR § 200.308 – Revision of budget and program plans: https://www.law.cornell.edu/cfr/text/2/200.308 (checked 2026-11-15)
- Office of Management and Budget (OMB), Guidance for Federal Financial Assistance (89 FR 30046, 2024 Uniform Guidance Revisions): https://www.federalregister.gov/documents/2024/04/22/2024-07496/guidance-for-federal-financial-assistance (checked 2026-11-15)
- National Science Foundation (NSF), Proposal and Award Policies and Procedures Guide (PAPPG) Chapter X – Grant Administration: https://new.nsf.gov/policies/pappg/24-1/ch-10-grant-administration (checked 2026-11-15)
- National Institutes of Health (NIH), NIH Grants Policy Statement Section 8.1 – Changes in Project and Budget: https://grants.nih.gov/grants/policy/nihgps/html5/section_8/8.1_changes_in_project_and_budget.htm (checked 2026-11-15)
- Federal Demonstration Partnership (FDP), Research Terms and Conditions (RTC) Agency Prior Approval Matrix: https://www.nsf.gov/bfa/dias/policy/fedrtc/appendix_a.pdf (checked 2026-11-15)
- Electronic Code of Federal Regulations (eCFR), 2 CFR § 200.407 – Prior written approval (prior approval): https://www.law.cornell.edu/cfr/text/2/200.407 (checked 2026-11-15)
Data: Federal Awarding Agency Prior Approval and Expanded Authorities Matrix
Comparative matrix of federal awarding agency prior approval policies and expanded authorities under 2 CFR 200.308 compiled from agency policy manuals and RTC matrices.
Period covered: 2024/2026. Coverage: United States.
| Federal Agency | 90-Day Pre-Award Costs | First No-Cost Extension | Carryover of Balances | Direct Line Rebudgeting | Participant Support Costs | Unbudgeted Subawards |
|---|---|---|---|---|---|---|
| NSF (PAPPG Chapter X) | Authorized up to 90 days at institutional risk without prior approval | Grantee authorized up to 12 months via Research.gov notification 10 days prior | Automatic carryover across budget periods for continuing grants | Unrestricted except where change in scope or key personnel occurs | Prior written approval required to transfer funds to other categories | Prior approval required if not included in approved proposal |
| NIH (GPS Section 8.1) | Authorized up to 90 days under expanded authorities (SNAP and non-SNAP) | Grantee authorized up to 12 months via eRA Commons notification 10 days prior | Automatic under SNAP; prior approval required if non-SNAP terms specify | Significant rebudgeting permitted unless scope changes or specific restriction | Prior written approval required from GMO to reallocate to other direct costs | Prior approval required for foreign components or unapproved subawards |
| DOE (Acquisition Guide) | Authorized up to 90 days at recipient risk for research awards | Prior approval required unless explicitly delegated in award agreement | Prior approval required between budget periods unless terms waive | Prior approval required if cumulative transfer exceeds 10% on awards over SAT | Prior written approval required to transfer funds out of participant support | Prior approval required for adding new subawards not in approved budget |
| DOD / ONR (RTC Matrix) | Authorized up to 90 days prior to award date under RTC terms | Grantee authorized up to 12 months with 10 days advance written notice | Automatic carryover of unobligated balances across fiscal years | Permitted without prior approval unless technical scope is altered | Prior written approval required to reallocate to other direct categories | Prior approval required for subawards not detailed in original proposal |
| USDA / NIFA (Standard Terms) | Authorized up to 90 days prior to award date under standard grants | Grantee authorized up to 12 months with written notice 10 days prior | Automatic carryover for multi-year awards unless Notice of Award restricts | Permitted within direct cost line items within agency variance margins | Prior written approval required to reallocate to other budget items | Prior approval required for adding subawards not approved in initial award |
| ED (EDGAR 34 CFR Part 75) | Prior approval required unless explicitly authorized in program regulations | Prior approval required under EDGAR 75.261 unless expanded authorities apply | Prior approval required between project periods for continuation awards | Prior approval required if cumulative transfers exceed 10% or alter scope | Prior written approval required to transfer participant support allocations | Prior approval required for third-party subgrants and unapproved subcontracts |
Sources
- 2 CFR 200.308 Revision of budget and program plans (accessed 2026-11-15)
- NSF PAPPG Chapter X Grant Administration (accessed 2026-11-15)
- NIH Grants Policy Statement Section 8.1 (accessed 2026-11-15)
- FDP Research Terms and Conditions Prior Approval Matrix (accessed 2026-11-15)
Compiled by CASRAI from the sources above. Free to reuse under CC BY 4.0 with attribution.