Written and maintained by CASRAI Editorial Board
Published · Last updated
On this page
General equipment information for planners and supply staff, not medical advice and not a decontamination procedure.
Short answer
A decon shower is a shower station used to rinse contaminants off people exposed to a hazardous substance, usually set up by a hospital or response agency for mass-casualty incidents. The main equipment choices in OSHA’s hospital guidance are a permanent shower, a portable reusable system, or a disposable system, and the guidance says permanent facilities are generally recommended over temporary equipment.
Definition and scope
In this guide, “decontamination shower” means equipment for patient and victim decontamination at a hospital or incident site. OSHA’s 2005 publication Best Practices for Hospital-Based First Receivers of Victims from Mass Casualty Incidents Involving the Release of Hazardous Substances (OSHA 3249-08N) says hospitals “may select from an array of decontamination shower options.” It creates no new OSHA obligations and is dated 2005, so read it as planning guidance.
This is a different thing from a laboratory emergency shower or eyewash used for a chemical splash on a worker; for that context see hydrofluoric acid safety. Related containment contexts are covered in BSL-3 laboratory requirements, where suit laboratories include a chemical decontamination shower on exit.
Types of decon shower systems
The table below lists categories described in OSHA 3249 and a 2014 planning template hosted by HHS ASPR TRACIE. It is not a ranking.
| Option | What the guidance says | Source |
|---|---|---|
| Permanent decontamination facility | Generally recommended over temporary equipment. Some activate by “simply unlocking the doors and turning on the water.” They need dedicated space and more maintenance than disposable systems. | OSHA 3249 |
| Portable, reusable system | Durable portable systems are designed to be cleaned and reused if the contaminant is not highly toxic or persistent. All portable systems require some set-up time, and they vary in size and in the number of people needed to set them up. | OSHA 3249 |
| Disposable system | Intended to be disposable, which simplifies the post-incident recovery phase. | OSHA 3249 |
| Interim rapid option | High-capacity, low-pressure hoses or showerheads on temperature-controlled water sources for rapid preliminary drenching. With multiple showerheads, ensure water flow is adequate at each. | OSHA 3249 |
| Internal or external decon area | Internal means designated shower(s) inside a fixed facility. External means a designated outside area that may use tents, a trailer or an open-air shower with a modesty curtain. | ASPR TRACIE / DCEHC template |
Decon tent and decon kit: what the sources mean
Decontamination tent (decon tent)
The ASPR TRACIE template lists tents among the ways to build an external decontamination area, alongside trailers and open-air showers with a modesty curtain. The same template says the area needs suitable identification (fixed or portable signage) and a perimeter barrier that clearly outlines safe and unsafe areas. OSHA advises hospitals to avoid locating the decontamination facility inside the emergency department.
Decontamination kit (decon kit)
In the template’s equipment and supplies list, kits are patient-handling supplies rather than a shower: “bag/tag kits” for collecting and identifying each patient’s personal effects, and “patient redress kits,” the supplies given to patients to wash themselves, dry off and redress. Product contents sold under the name “decon kit” vary by seller, and neither source defines a standard contents list.
Activation time and set-up
OSHA cites a suggestion that a system be operational within 2 to 3 minutes of notification, then notes that few temporary or portable systems can realistically be activated that quickly. According to Hospital A, “activation periods of 10 to 15 minutes are more typical for temporary decontamination facilities, even with highly trained and experienced staff,” and inexperienced staff “might require two to four times longer” to set up. Experience from drills is one of the factors hospitals reported using when selecting equipment.
Wastewater containment
Containment is part of the equipment decision, not an afterthought. OSHA describes portable systems with a containment device built into the base (a low wall a few inches high plus plastic lining); a portable electric pump of about 2.5 gallons per minute in one example moves the water into a rubber bladder or barrel. Storage barrels and bladders at the interviewed hospitals ranged from 50 to 2,500 gallons, and larger multi-head systems generate wastewater faster and tend to have larger floor-level containment. Collected water is held for testing, treatment and release as authorities decide.
Permanent installations differ: Hospitals A and C use underground tanks, while Hospital B has an agreement with its municipal wastewater treatment facility to drain to the sanitary sewer and notifies it when the shower is used. The ASPR TRACIE template lists the same families of options: an above-ground basin per decon area pumped into a bladder or container, below-ground storage containers, or sewer or storm drainage with notice to the water authority.
Selection factors reported in OSHA’s hospital interviews
These are factors the interviewed hospitals reported, restated as a checklist. OSHA does not present them as a requirement or ranking.
- Prior experience with the system in drills.
- Quick set-up by minimal personnel with little storage space.
- Compatibility with other community equipment, such as the fire department’s, so systems can be joined into a larger shower area.
- Cost and any funding-source requirements.
- Space available for a permanent shower.
- Community needs, meaning how often and how many people.
- Operation in harsh weather. Enclosed facilities should provide fresh-air circulation, and OSHA advises consulting a ventilation engineer or Certified Industrial Hygienist early in design.
OSHA’s interviewed hospitals described matching equipment to the needs of the hospital and its community.
Common misunderstandings
- “A decon shower is the same as a lab safety shower.” It is not. Mass-casualty decon equipment serves many people at once and includes wastewater handling; lab emergency showers address a single exposed worker.
- “Portable means ready in minutes.” OSHA reports 10 to 15 minutes as more typical for temporary facilities, even with trained staff.
- “A decon kit includes the shower.” In the template, kits are bag/tag and redress supplies.
- “Decon equipment replaces protective gear.” Responder protection is a separate topic; see gas mask types and bloodborne pathogens PPE, and chemical spill kits for small laboratory spills.
FAQ
What is a decontamination shower?
It is a shower station for rinsing contaminants off people exposed to a hazardous substance. OSHA 3249 describes fixed, portable reusable and disposable options for hospitals receiving victims of hazardous-substance releases.
What are decontamination showers used for, and how do the types differ?
They support mass-casualty decontamination at hospitals or incident sites. Permanent units need dedicated space and maintenance; portable units trade set-up time for flexibility; disposable units simplify recovery; and all of them need a plan for wastewater.
Is a decontamination tent a decon shower?
A tent can house the shower area. The ASPR TRACIE template lists tents, trailers and open-air showers with a modesty curtain as external decontamination areas.
How is decon shower wastewater handled?
Options in the ASPR TRACIE template include above-ground basins pumped into a bladder or container, below-ground storage containers, or sewer or storm drainage with notice to the water authority. OSHA describes portable systems with containment built into the base and permanent systems with underground tanks or a sewer agreement.
Sources
- OSHA, Best Practices for Hospital-Based First Receivers of Victims from Mass Casualty Incidents Involving the Release of Hazardous Substances, OSHA 3249-08N, 2005: osha.gov. Checked 2026-11-01. Guidance only; creates no new OSHA obligations.
- District of Columbia Emergency Healthcare Coalition, Acute Care Facilities Decontamination Planning Template, May 2014, hosted by HHS ASPR TRACIE: files.asprtracie.hhs.gov. Checked 2026-11-01. A local coalition guidance document, not a federal rule.