Floating offshore wind uses wind turbines mounted on floating substructures that are held in place by mooring lines and anchors, so they can operate in water too deep for fixed foundations. The main substructure families are semi-submersible, barge, spar and tension leg platform (TLP), and each fits different water depths, installation methods and mooring designs.
Short answer
A floating offshore wind turbine does not stand on the seabed. It sits on a buoyant substructure, anchored by moorings, and exports power through a flexible (dynamic) cable. Researchers and engineers treat the field as a design-basis problem: the choice of substructure sets how the turbine is assembled, towed, moored and inspected, and international standards such as DNV-ST-0119 and the IEC 61400-3-2 series define the design requirements.
Definition and scope
In standards language the object of study is the floating offshore wind turbine (FOWT). The 2019 IEC technical specification IEC TS 61400-3-2, as catalogued by the Estonian Centre for Standardisation and Accreditation (EVS), sets out additional requirements for the external conditions at a FOWT site and essential design requirements. It covers ship-shaped structures and barges, semi-submersibles, spar buoys and tension-leg platforms or buoys, and it applies to unmanned floating structures carrying one horizontal-axis turbine. It is used together with IEC 61400-1 and IEC 61400-3-1.
The scope reaches beyond turbines. DNV-ST-0119, the DNV standard for floating wind turbines, covers floating offshore substations as well as turbines, and addresses design, construction and in-service inspection. Its stated aim is to provide an internationally acceptable level of safety by defining minimum requirements.
Why water depth drives the field
The US Department of Energy states that about two-thirds of US offshore wind energy potential lies over waters too deep for fixed-bottom foundations. That resource is the reason floating designs are studied. The DOE Floating Offshore Wind Shot sets a target to reduce the cost of floating offshore wind energy by more than 70%, to $45 per megawatt-hour by 2035, at deep-water sites far from shore. The Shot is a cost target and not a description of present costs.
How a floating turbine is held in place and connected
A floating substructure is kept on station by a mooring system made of lines and anchors. The Guide to Floating Offshore Wind, produced by BVG Associates with ORE Catapult, The Crown Estate, Crown Estate Scotland and the Floating Offshore Wind Centre of Excellence, notes that semi-submersible, barge and spar substructures can use a wide range of mooring and anchor configurations. A tension leg platform is different: its stability comes from the mooring system, with lines that are vertical or near-vertical, so the anchors must resist strong vertical pull. The guide gives driven piles and suction anchors as examples of anchors that can do this.
Power leaves the turbine through a dynamic cable, because the substructure moves. The same guide describes floating offshore substations, which collect power from turbines, step up the voltage with transformers and send it ashore through high-voltage dynamic export cables. Those cables must carry voltages above 66 kV and withstand fatigue and cyclic movement over the project life. Floating substations are needed at depths above 150 m, where a fixed-bottom substation is not feasible, and are moored with steel cables, chains or fibre ropes. The only full-scale floating substation the guide reports demonstrated is at Fukushima, Japan (2013), serving three turbines with a total of 16 MW through a 66 kV cable, on a spar designed by Japan Marine United Corporation.
Platform types
The four main substructure types differ by the water depth the guide gives as suitable (semi-submersible and barge over 40 m, tension leg platform over 80 m, spar over 100 m), by how the turbine is installed and by what the type implies for mooring. The dataset on this page sets these out side by side; the notes here add the context a dataset cannot hold.
Semi-submersible
A semi-submersible usually has three or four outer buoyant columns connected by pontoons or trusses, often ballasted for stability. The guide lists it as suitable for depths greater than 40 m. Its draft is smaller than a spar’s, which allows the turbine to be installed at the quayside, and tugs and anchor-handling vessels can be used in broad weather windows. It is the largest type by length and width and has higher mass than a TLP, so storage and marshalling need large sea and land areas. At full scale, the guide reports that only the Kincardine project (Principle Power’s WindFloat, five turbines) has been installed.
Barge
A barge has a single hull piercing the waterline. Design variables include the material (concrete or steel), the hull shape (square or cylindrical) and whether there is a moonpool and how large it is. Like the semi-submersible it is listed for depths greater than 40 m. Because the combined structure is stable in transport, the turbine can be erected in a sheltered harbour and the whole assembly towed out. The guide names BW Ideol’s Damping Pool and Saitec’s SATH as installed examples.
Spar
A spar is a tall cylinder with dense ballast in its lower part, listed for depths above 100 m. Equinor used this type for its first three North Sea projects, including Hywind Scotland. Its large draft limits the sites suitable for tow-out and tow-back, and quayside assembly needs deep water; floating installation vessels in sheltered deep water, such as Norwegian fjords, are an option but add cost. The guide also records that a spar has the highest tilt in normal operation of all the types, and that active ballasting cannot correct it.
Tension leg platform
A TLP is listed for depths above 80 m. Final assembly in port followed by tow-out is not possible, so the turbine is either assembled at the site through a weather-sensitive floating-to-floating lift or pre-assembled with the TLP on a vessel. After installation it has the lowest structural mass and, apart from spars, the lowest motions. The mooring and anchors cost more than for other types because of higher loads and redundancy requirements, and the importance of the mooring to stability may cause reluctance to use TLPs in seismically active areas. SBM Offshore’s design was the first full-scale TLP demonstrator in offshore wind, installed at Provence Grand Large, France, in 2023.
Other substructure concepts
The guide also lists concepts outside the four main families. The table below summarises them.
| Concept | Feature described by the guide | Named examples |
|---|---|---|
| Counterweight | Shallow for transport, with stability from mass located at depth; raising and lowering the counterweight adds mechanical complexity | Saipem’s Hexafloat |
| Single-point pivot | Turret or single-point moorings, proven in floating production vessels; the turbine does not need a yaw system | X1 WIND’s PivotBuoy, Aerodyn’s Nezzy2, Saitec’s SATH |
| Downwind rotor | Enables tower braces, guyed or inclined towers | PivotBuoy, Nezzy2 |
| Multiple rotors | Two turbines per substructure | Hexicon, Nezzy2, Mingyang’s OceanX |
| Vertical axis | Vertical-axis turbine on a floating substructure | SeaTwirl’s S1 and S2 |
| Combined wind and wave | Wind turbine combined with wave energy capture | Floating Power Plant |
Concrete or steel
Materials matter for design and supply. The guide states that steel plate prices have swung by up to 50% within a year, while concrete prices tend to be more stable. Concrete substructures are heavier and need more effort to lift or tow; concrete is more vulnerable to freeze-thaw damage and steel to corrosion. Hywind Demo (30 MW, 2017) used steel spars, whereas Hywind Tampen (88 MW) used concrete spars.
Design standards: what governs a floating turbine
Two documents anchor the standards picture. They do different jobs, and the status of the IEC document has changed.
- IEC 61400-3-2. The 2019 technical specification, IEC TS 61400-3-2:2019, is listed by EVS as withdrawn from 22 January 2025 and replaced by IEC 61400-3-2:2025. The scope described above is that of the 2019 specification; anyone citing floating-turbine design requirements should cite the current edition.
- DNV-ST-0119. DNV’s page shows the edition as 2026-10. It extends existing wind and offshore standards to floating turbines and is the basis for classification under DNV-RU-OU-0512 and for certification under DNV-SE-0422. It is also used as a contract reference.
For a research team, the practical consequence is traceability: a model validation report or design study should name the standard and edition it used, because the IEC and DNV documents have moved on from earlier versions.
Where it matters for research and planning
- Resource assessment. The DOE figure that about two-thirds of US offshore wind potential lies over deep water frames floating wind as an access-to-resource question. For wind resource data and modelling, see the energy and renewables discipline hub.
- Cost. The DOE Shot gives a numeric target ($45/MWh by 2035, more than 70% reduction) against which cost-reduction studies can be framed.
- Installation and port logistics. Quayside installation, harbour assembly, tow-out limits and weather windows differ by substructure, as the platform type notes show. These constraints are design inputs, not afterthoughts.
- Mooring, anchors and seabed. TLP anchor loads and seismic considerations are an example of how site geology feeds back into the substructure choice.
- Cables and substations. Dynamic cable fatigue and floating substation demonstration status are open engineering topics, since the guide reports only one full-scale floating substation.
Floating wind sits next to other marine energy topics. The CASRAI guide to ocean energy covers marine energy sources, and the broader lab operations hub covers practical research-facility practice.
Common misunderstandings
“Floating” means the turbine is free-floating
It is not. A floating substructure is moored to the seabed with anchors, and in the TLP case the mooring lines carry the stability load directly.
All floating platforms behave the same
They differ in depth range, installation route, tilt, mass and mooring demands. A spar has the highest tilt in normal operation; a TLP has the lowest structural mass once installed; a barge can be fitted with its turbine in a sheltered harbour.
The depth thresholds are hard limits
The 40 m, 80 m and 100 m figures are the guide’s statements of the water depth for which each type is suitable. They are not regulatory limits, and the DOE page does not state a single depth that separates fixed from floating.
The cost target is the current cost
The $45 per megawatt-hour figure is a 2035 target of the DOE Floating Offshore Wind Shot. It is not a price or a measured cost today.
A 2019 standard still applies
IEC TS 61400-3-2:2019 is withdrawn and has been replaced by the 2025 edition of IEC 61400-3-2.
Sources
- DNV: DNV-ST-0119 Floating wind turbines, checked 2026-11-17
- EVS: IEC TS 61400-3-2:2019 catalogue entry, checked 2026-11-17
- Guide to Floating Offshore Wind: Floating technology, checked 2026-11-17
- US Department of Energy: Floating Offshore Wind Shot, checked 2026-11-17
Data: Floating offshore wind substructure types: suitable water depth, installation and mooring implications
Compares the four main floating offshore wind substructure types (semi-submersible, barge, spar, tension leg platform) by the water depth the Guide to Floating Offshore Wind gives as suitable, the installation route it describes, and its mooring and anchor implications. Compiled by CASRAI from the guide's floating technology page; no values are estimated.
Coverage: Global.
| Substructure type | Suitable water depth, greater than (m) | Installation route described | Mooring and anchor implication |
|---|---|---|---|
| Semi-submersible | 40 | Quayside turbine installation possible because of smaller draft; tugs and anchor-handling vessels in broad weather windows | Wide range of mooring and anchor configurations |
| Barge | 40 | Turbine erected in sheltered harbour, then whole structure towed out | Wide range of mooring and anchor configurations |
| Spar | 100 | Quayside assembly needs deep water; floating installation vessels in sheltered deep water add cost; large draft limits tow-out sites | Wide range of mooring and anchor configurations |
| Tension leg platform | 80 | Port assembly then tow-out not possible; site assembly by floating-to-floating lift or pre-assembly on a vessel | Near-vertical lines; anchors must resist strong vertical pull (driven pile or suction anchor); higher mooring and anchor cost |
Sources