The Sanford Underground Research Facility (SURF) is an underground science laboratory in Lead, South Dakota, built in the former Homestake gold mine. Its operator describes it as the deepest underground laboratory in the United States, at 4,850 feet, and it is managed by the South Dakota Science and Technology Authority (SDSTA) under a cooperative agreement with the U.S. Department of Energy (DOE) Office of Science. This guide explains what SURF is, how researchers get access, who pays for it and where its geothermal work fits.
Short answer
SURF is a research site, not a tourist attraction with a lab attached. Physics experiments on dark matter, neutrinos and rare nuclear processes occupy most of the public attention, but the facility also hosts biology, geology and engineering work. Researchers who want to use it follow a written proposal path that starts with the Experiment Implementation Program and ends with a signed User Agreement. A South Dakota state authority operates it, and DOE’s Office of Science funds science operations through a cooperative agreement.
Definition and scope
SURF is the research laboratory that took over the Homestake Mine after the mine closed in 2001. According to the laboratory’s own history page, Homestake operated from 1876 to 2001 and produced about 41 million ounces of gold and 9 million ounces of silver over roughly 125 years. The 4850 Level, the main research level, was dedicated in 2009 after an extensive dewatering of the mine.
A 2022 overview paper by SURF’s Science Director, Jaret Heise, describes the facility as having a surface campus and underground campuses at the 4850-foot level. It gives the 4850 Level as about 1,500 m deep, with an overburden of about 4,300 meters of water equivalent (m.w.e.), the unit physicists use to describe how much rock shields an experiment from cosmic rays. The same paper lists ultra-low-background assay capability and electroformed copper production among the facility’s services, and describes proposals for additional underground space on the 4850 Level and on a 7400 Level at about 2,300 m (6,500 m.w.e.).
The same overview reports the scale of the research community at the time it was written: 60 groups had run programs at SURF, 29 programs were ongoing and 21 were regularly onsite. About 350 researchers were onsite (excluding DUNE), drawn from about 600 collaboration members at 87 institutions in nine countries, and SURF employed 203 full- and part-time staff. Treat these as 2022 figures, not current counts.
How researchers use SURF in practice
SURF publishes an explicit proposal path for outside researchers. The steps below follow the order given on the laboratory’s proposal-guidelines page.
- Read the Experiment Implementation Program (document SCI-1000-S-001).
- Read the Experiment Integration and Support document.
- Draft an Experiment Planning Statement (form SCI-1000-F-001) describing the project.
- Contact the SURF Science Director, who is employed by the SDSTA.
- Complete the User Agreement (form SCI-1000-F-002). It references the underground access waiver, the SURF Environment, Safety and Health (ESH) Standards and the Publication Guidelines.
The same page lists the supporting paperwork by number: a User Agreement Acknowledgement (SCI-1000-F-004), the Publication Guidelines (SCI-1000-S-003) and the Acknowledgement of Risk Waiver (EL-1000-F-001). For a research office, the practical point is that three things are agreed in writing before anyone goes underground: the experiment plan, the user terms and the safety standards. The overview paper adds that the Laboratory Director allocates facility resources on the basis of merit review.
Underground access also draws on skills outside physics. The laboratory’s history page notes that the underground spaces are used to train civil and mining engineers and to support mine rescue operations; see the CASRAI guide to mine rescue for how that discipline is organised.
Who runs and pays for SURF: a roles table
SURF is a good example of a mixed-governance research facility, and the table below separates the roles that the sources describe. It is useful when a proposal or award needs to name the right party.
| Role | Who, according to the sources | Source |
|---|---|---|
| Operator and manager | South Dakota Science and Technology Authority (SDSTA), formed in 2004 by Governor Mike Rounds and the State Legislature | SURF, Our Story |
| Federal funder of science operations | DOE Office of Science, through a cooperative agreement (funding since fall 2011, first through sub-contracts with national laboratories, and through a cooperative agreement since fall 2019) | SURF, Our Story; Heise 2022 |
| Private and state origins | T. Denny Sanford pledged $70 million; the State of South Dakota committed more than $40 million; Barrick Gold donated land | SURF, Our Story |
| Point of contact for new experiments | SURF Science Director (SDSTA) | SURF, Proposal Guidelines |
| Allocation of facility resources | Laboratory Director, by merit review | Heise 2022 |
| Community body | SURF User Association, launched in 2020 and open to the global underground science community | Heise 2022 |
| Low-background assay campus | Black Hills State University operates the BHSU underground campus | Heise 2022 |
A cooperative agreement differs from a contract in that the federal agency is substantially involved in the work. For funding teams comparing how infrastructure like this is supported, the CASRAI guide to research infrastructure funding sets out the wider landscape.
Major experiments and related concepts
The laboratory’s history page names five anchor activities. Each is listed here with what the source says about it.
LUX and LZ (dark matter)
LUX, the Large Underground Xenon experiment, sat in the renovated Davis Cavern. After an initial 80-day run it was named the most sensitive dark matter detector in the world in October 2013, a result confirmed in 2016, the year the experiment was decommissioned. Its successor LZ (LUX-ZEPLIN) began operating in 2021 and announced first results on July 7, 2022.
Majorana Demonstrator (neutrinoless double-beta decay)
The Majorana Demonstrator collected data from 2015 to 2021 while searching for neutrinoless double-beta decay, and its final results came in early 2023. The collaboration is joining another germanium experiment to form LEGEND, which will ultimately use one ton of enriched germanium.
CASPAR (nuclear astrophysics)
The Compact Accelerator System for Performing Astrophysical Research (CASPAR) was installed on the 4850 Level in 2015. It studies how elements heavier than iron are created in collapsing stars.
LBNF/DUNE (neutrinos)
Excavation for the Long-Baseline Neutrino Facility and the Deep Underground Neutrino Experiment began in 2019 and was completed in 2024, with more than 800,000 tons of rock removed.
Beyond physics
The laboratory describes research on microbial life in its extreme environment, which it links to possible work on medicines, biofuels and carbon sequestration. It also describes engineering work, including commercial research and development such as Caterpillar’s Minestar tracking technology.
Where it matters: geothermal research and energy
The link to energy research is the Center for Understanding Subsurface Signals and Permeability (CUSSP). PNNL describes CUSSP as one of 11 Energy Earthshot Research Centers funded by DOE in 2023, with a goal of predicting and controlling fluid flow through fracture networks in enhanced geothermal systems (EGS). Pacific Northwest National Laboratory leads it, with Argonne National Laboratory, Clemson University, Colorado School of Mines, Lawrence Berkeley National Laboratory, Purdue University, the University of California, Irvine, the University of Illinois Urbana-Champaign, the University of Maryland and the University of New Mexico as partners. Its timeline runs from fiscal year 2023 through fiscal year 2027. For more on the lead laboratory, see the CASRAI guide to Pacific Northwest National Laboratory.
PNNL says the project uses an EGS testbed at SURF. SURF’s instruments can collect several geophysical signals at once, including temperature, strain and seismic activity, and the team deploys time-lapse 4D electrical resistivity tomography that its members developed. Laboratory flow experiments use rocks from SURF. The project is organised into one thrust on micro- to core-scale processes and one on field-scale assimilation and validation, with modeling and simulation as a cross-cutting theme.
SURF’s own history page frames the same work more broadly: researchers from several national laboratories study how hot fluids flow through rock fractures over time. The 2022 overview paper also lists the EGS Collab SIGMA-V project among the work using alcoves on the 4100 Level, and notes that some geothermal projects could need access below the 5000 Level.
For a research office, the useful pattern is that a facility can host a multi-institution, multi-year funded center without being the lead institution: PNNL leads CUSSP and the funding comes from DOE, while SURF supplies the site and instrumentation access.
Common misunderstandings
“SURF was always a national science laboratory.”
It was not. In December 2010 the National Science Board declined to fund further design of the Deep Underground Science and Engineering Laboratory (DUSEL), the proposal for a large national underground laboratory at the site. DOE, through Lawrence Berkeley National Laboratory, agreed in 2011 to support science operations, and the current arrangement is a DOE Office of Science cooperative agreement together with SDSTA funds.
“It is a gold mine you can visit.”
The mine stopped operating in 2001. The Sanford Lab Homestake Visitor Center in Lead is free and open Monday to Saturday, 9:00 to 4:00, according to the laboratory, but the underground research areas are reached through the user process described above.
“It only does physics.”
The overview paper lists physics, biology, geology and engineering among its disciplines, and the CUSSP geothermal testbed is an energy research project.
“The numbers on the web are current.”
The user counts and staff size above come from a 2022 paper, and SURF’s own page gives some dates in more than one place, so check the facility’s current pages for anything you plan to cite in a proposal or award document.
Frequently asked questions
Where is the Sanford Underground Research Facility?
It is in Lead, South Dakota, in the former Homestake Mine, and the laboratory’s address is 630 E. Summit St., Lead, SD 57754.
How deep is SURF?
The laboratory states that it is the deepest in the United States at 4,850 feet. A 2022 overview paper gives the 4850 Level as about 1,500 m (about 4,300 m.w.e.) and describes the deepest currently accessible elevation as 5000 Level.
Who operates SURF?
The South Dakota Science and Technology Authority operates it under a cooperative agreement with the DOE Office of Science.
How can a researcher propose an experiment?
Follow the laboratory’s proposal-guidelines sequence: read the Experiment Implementation Program and the Experiment Integration and Support document, draft an Experiment Planning Statement (SCI-1000-F-001), contact the Science Director and complete the User Agreement (SCI-1000-F-002).
What does SURF have to do with geothermal energy?
PNNL’s CUSSP center, funded by DOE for fiscal years 2023 to 2027, uses an enhanced geothermal system testbed at SURF to study fluid flow through fracture networks.
Sources
- Sanford Underground Research Facility: Our Story, checked 2026-11-20
- Sanford Underground Research Facility: Proposal Guidelines, checked 2026-11-20
- Pacific Northwest National Laboratory: Center for Understanding Subsurface Signals and Permeability (CUSSP), checked 2026-11-20
- arXiv: The Sanford Underground Research Facility (J. Heise, 2022), checked 2026-11-20
Data: SURF timeline: mine, governance, funding and science milestones, 1876-2024
Compiled timeline of milestones for the Sanford Underground Research Facility, grouped by type (mine operation, governance, funding, facility, science). Each row is taken from the facility's own history page, a 2022 overview paper by its Science Director or the PNNL CUSSP project page.
Period covered: 1876-2024. Coverage: Lead, South Dakota, USA.
| Period | Milestone | Category | Source |
|---|---|---|---|
| 1876-2001 | Homestake Mine operates in Lead, South Dakota (about 41 million oz gold, 9 million oz silver) | Mine operation | SURF Our Story |
| Mid-1960s | Brookhaven Solar Neutrino Experiment built on the 4850 Level | Science | SURF Our Story |
| 2001 | Homestake closes | Governance | SURF Our Story |
| 2004 | SDSTA formed by Governor Rounds and the State Legislature | Governance | SURF Our Story |
| 2007 | DUSEL created (now SURF) | Governance | SURF Our Story |
| 2009 | 4850 Level dedicated after dewatering | Facility | SURF Our Story |
| 2010 | National Science Board declines to fund further DUSEL design (December) | Funding | SURF Our Story |
| 2011 | DOE, through Lawrence Berkeley National Laboratory, agrees to support science operations | Funding | SURF Our Story |
| 2013 | LUX named most sensitive dark matter detector after 80-day run (October) | Science | SURF Our Story |
| 2015 | CASPAR installed; Majorana Demonstrator begins data collection | Science | SURF Our Story |
| 2019 | DOE Office of Science cooperative agreement begins (fall); LBNF/DUNE excavation begins | Funding | Heise 2022; SURF Our Story |
| 2021 | LZ begins operating | Science | SURF Our Story |
| 2022 | LZ first results announced (July 7) | Science | SURF Our Story |
| 2023 | CUSSP funded by DOE (FY2023-FY2027) with an EGS testbed at SURF | Funding | PNNL CUSSP |
| 2024 | LBNF/DUNE excavation completed (more than 800,000 tons of rock) | Facility | SURF Our Story |
Sources
- SURF: Our Story (accessed 2026-11-20)
- Heise, The Sanford Underground Research Facility (arXiv 2203.08293) (accessed 2026-11-20)
- PNNL: CUSSP (accessed 2026-11-20)
Compiled by CASRAI from the sources above. Free to reuse under CC BY 4.0 with attribution.