36 CFR Part 800 implements Section 106: how federal agencies review effects on historic properties, who consults, and the 30- and 15-day periods.

Written and maintained by CASRAI Editorial Board

Published

On this page

36 CFR Part 800 is the Advisory Council on Historic Preservation (ACHP) regulation titled “Protection of Historic Properties”. It sets out how a federal agency must take into account the effects of its undertakings on historic properties before it approves, funds, permits or licenses them. That obligation is known as the Section 106 process, after the section of the National Historic Preservation Act it implements. For researchers, the practical meaning is that a federally funded, permitted or licensed project that can affect an archaeological site, building, district, structure or object listed in or eligible for the National Register of Historic Places has to run through this process before the federal decision is made.

What 36 CFR Part 800 is and who runs it

Part 800 is organized into three subparts and one appendix, as published in the Code of Federal Regulations (Cornell LII, 36 CFR Part 800). Subpart A covers purposes and participants (sections 800.1 and 800.2). Subpart B, “The Section 106 Process”, covers sections 800.3 through 800.13. Subpart C, “Program Alternatives”, covers sections 800.14 through 800.16, which include the definitions. Appendix A sets out the criteria for ACHP involvement in reviews. The statutory authority cited is 16 U.S.C. 470s, and the rule’s source is 65 FR 77725, published December 12, 2000.

The regulation is issued by the ACHP (see the CASRAI guide to the Advisory Council on Historic Preservation). The review is carried out by the federal agency official responsible for the undertaking, who consults with the SHPO or THPO, tribes and other consulting parties, with the ACHP participating in some cases. The ACHP’s own introduction to Section 106, as described on its site on 2026-11-18, lists the stages as: determine whether Section 106 applies, initiate the process by identifying participants and planning public involvement, identify historic properties, assess effects, and resolve adverse effects.

Who and what it applies to

Section 800.16 supplies the definitions that decide whether Part 800 reaches a project. An undertaking is a project, activity or program funded in whole or in part under the direct or indirect jurisdiction of a federal agency, including projects carried out by or on behalf of the agency, those carried out with federal financial assistance, and those requiring a federal permit, license or approval. A historic property is any prehistoric or historic district, site, building, structure or object included in, or eligible for inclusion in, the National Register of Historic Places, and the definition includes artifacts, records and remains related to such properties, as well as properties of traditional religious and cultural importance to Indian tribes and Native Hawaiian organizations. The area of potential effects (APE) is the geographic area within which an undertaking may directly or indirectly cause alterations in the character or use of historic properties (36 CFR 800.16).

This is why the rule matters to research offices. A grant funded under federal financial assistance, or a field project that needs a federal permit, can be an undertaking even when the principal investigator never deals with the federal agency’s compliance staff directly. For archaeologists and historians, the definition of historic property is also the link between the regulation and the field: the “artifacts, records, and remains” wording ties collections and documentation to the same review. The archaeology overview explains how the discipline’s fieldwork relates to this regulatory layer.

What Part 800 requires, section by section

The table below maps each section of Subpart B to what it governs, using the section titles in the CFR. The day-count data table further down covers the only review periods identified in the sections read.

Section Title What it governs
800.3 Initiation of the section 106 process The agency official decides whether the action is an undertaking and whether it has the potential to cause effects; identifies the State or Tribal Historic Preservation Officer and other participants.
800.4 Identification of historic properties Identification of historic properties in the area of potential effects.
800.5 Assessment of adverse effects Assessment of whether an undertaking has an adverse effect, and the finding that follows.
800.6 Resolution of adverse effects Consultation to avoid, minimize or mitigate; the memorandum of agreement.
800.7 Failure to resolve adverse effects The section on failure to resolve adverse effects.
800.8 Coordination with the National Environmental Policy Act Coordination between Section 106 and NEPA.
800.9 Council review of section 106 compliance The Council’s review of Section 106 compliance.
800.10 Special requirements for protecting National Historic Landmarks Special requirements for National Historic Landmarks.
800.11 Documentation standards Documentation standards.
800.12 Emergency situations Emergency situations.
800.13 Post-review discoveries Post-review discoveries.

Subpart C then provides for program alternatives under section 800.14, including programmatic agreements, and sections 800.15 and 800.16 follow. A programmatic agreement is defined in section 800.16 as an agreement made under section 800.14(b).

The Section 106 process in practice

Step 1: Decide whether there is an undertaking

Under 36 CFR 800.3, the agency official determines whether the proposed action is an undertaking as defined in 800.16(y) and, if so, whether it is a type of activity with the potential to cause effects on historic properties. If the action is not an undertaking, or has no potential to cause effects, the agency has no further Section 106 obligation. The agency official also identifies the appropriate State Historic Preservation Officer (SHPO) or Tribal Historic Preservation Officer (THPO) at this stage. A THPO is the tribal official appointed by the tribe’s chief governing authority who has assumed the SHPO’s Section 106 responsibilities on tribal lands.

Step 2: Identify participants and historic properties

Consulting parties are identified together with the SHPO or THPO. Indian tribes and Native Hawaiian organizations that request in writing to be consulting parties must be granted that status. Section 800.4 then governs how historic properties in the APE are identified, which is where archaeological survey work typically sits.

Step 3: Assess effects

Under 36 CFR 800.5, an undertaking has an adverse effect when it may alter, directly or indirectly, any of the characteristics of a historic property that qualify it for the National Register in a way that diminishes the property’s integrity. The agency must consider reasonably foreseeable effects that may occur later in time, be farther removed in distance or be cumulative. The regulation’s examples of adverse effects include physical destruction of or damage to all or part of the property, removal of the property from its historic location, and transfer of the property out of federal control without adequate and legally enforceable restrictions or conditions to ensure long-term preservation. If the agency finds no adverse effect, it notifies the consulting parties, and the SHPO or THPO has 30 days from receipt to respond; if there is no objection, the agency may proceed. If there is an adverse effect, the agency moves to consultation under 800.6.

Step 4: Resolve adverse effects

Under 36 CFR 800.6, the agency official consults with the SHPO or THPO and other consulting parties, including tribes and Native Hawaiian organizations, to develop and evaluate alternatives or modifications that could avoid, minimize or mitigate adverse effects. The public receives information and has an opportunity to comment. The usual outcome is a memorandum of agreement (MOA) signed by the agency official and the SHPO or THPO, and by the Council if it participates. The agency sends a copy of the executed MOA, with the required documentation, to the Council before approving the undertaking. The ACHP must tell the agency within 15 days of notice or request whether it will participate. An executed MOA is the evidence that the agency has satisfied Section 106; copies go to each consulting party, and only the signatories can amend or terminate it.

Timeline phases and the review periods

Part 800 does not set one overall calendar for a review; the length depends on how much identification work the area requires and whether adverse effects are found. What it does fix are a few response periods, collected in the data table below. Two matter most: the 30 days allowed to a SHPO or THPO to respond to a request for review of a finding or determination under 800.3 and 800.5, and the 15 days allowed to the Council to say whether it will participate in consultation under 800.6. If a SHPO or THPO does not respond within 30 days of receiving a request for review of a finding or determination, the agency may proceed to the next step in the process or consult the Council.

In sequence, a review passes through five phases: the threshold decision, the initiation and planning of consultation, the identification effort, the effect assessment, and, only where adverse effects exist, resolution through an MOA. Section 800.13 is titled Post-review discoveries, which indicates the regulation anticipates properties turning up after a review has closed.

Common mistakes

These errors follow directly from the text of the sections above.

  • Assuming a project is outside the rule because the researcher is not the federal agency. An undertaking includes projects carried out with federal financial assistance and those requiring a federal permit, license or approval, so the trigger is the federal connection, not who performs the work.
  • Treating the 30-day period as automatic approval of the project. The 30 days is a period for the SHPO or THPO to respond to a request for review; what the agency may do after it lapses is stated in 800.3 and 800.5 as proceeding to the next step or consulting the Council, not as a finding that no historic property exists.
  • Limiting the idea of historic property to buildings. The definition covers districts, sites, structures and objects, plus artifacts, records and remains, and properties of traditional religious and cultural importance to tribes and Native Hawaiian organizations.
  • Looking only at direct physical damage. The adverse-effect criteria include indirect effects and reasonably foreseeable later, farther or cumulative effects.
  • Approving before the MOA is executed. Where there is an adverse effect, the agency sends the MOA and documentation to the Council before approving the undertaking.
  • Leaving out tribes and Native Hawaiian organizations. Those that request in writing to be consulting parties must be granted that status.

Section 800.8 coordinates Section 106 with the National Environmental Policy Act; the CASRAI guide to the National Environmental Policy Act covers the parallel environmental review. For the grant side of federally funded research, the framework is described in the Uniform Guidance (2 CFR 200), which governs how awards are administered but is separate from the preservation review described here.

Status: the 2026 proposal to revise Part 800

As described on the ACHP’s news page on 2026-11-18, ACHP members voted in July 2026 to move forward with a Notice of Proposed Rulemaking (NPRM) revising 36 CFR Part 800. The draft NPRM is in interagency review with the Office of Information and Regulatory Affairs and has not been published in the Federal Register. A proposal is not a rule: the text described above remains the regulation until a final rule is issued, and anyone planning a review should read the current CFR text and any rulemaking notices when they are published.

Sources

Data: Response periods and decision owners in 36 CFR Part 800

Compiled from the text of 36 CFR 800.3, 800.5 and 800.6 as published by Cornell LII: the three response periods stated in those sections, who must act within each, and what the regulation says may follow. No other day counts were identified in the sections read.

Period covered: Text read 2026-11-18. Coverage: United States.

Response periods and decision owners in 36 CFR Part 800
ProvisionParty that must respondPeriod (days)Subject of the responseStated consequence
36 CFR 800.3SHPO or THPO30Request for review of a finding or determinationAgency may proceed to the next step or consult the Council
36 CFR 800.5SHPO or THPO30Finding of no adverse effect, from receiptIf no objection, the agency may proceed
36 CFR 800.6Advisory Council on Historic Preservation15Whether the Council will participate in resolving adverse effectsCouncil must say whether it will participate

Sources

Compiled by CASRAI from the sources above. Free to reuse under CC BY 4.0 with attribution.

Follow CASRAI

Research-administration guidance, standards updates and independent tool reviews.

Ask CASRAI · free to try

Ask about 36 CFR Part 800: Section 106 Review, Section by Section

2 free questions a day, no account.

An AI assistant for research: funder rules, compliance, methods and publishing. It links the sources behind its answers and labels answers that come from a web search.

Answers draw on CASRAI's guides and dictionary plus the federal and funder documents we index: Federal Register, Grants.gov, Regulations.gov and UKRI.

Works on this site and inside Claude, Cursor and the AI tools you already use.

Everything CASRAI publishes — this page, the dictionary, the guides and the news — stays open to read, with no account and no card.

Referenced across the research world

University of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logoUniversity of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logo
  • University of Cambridge logo
  • Columbia University logo
  • Crossref logo
  • University of Edinburgh logo
  • Harvard University logo
  • University of Oxford logo
  • Princeton University logo
  • Stanford School of Medicine logo
  • University College London logo
  • ORCID logo

View CASRAI adoption →