Skip to main content
v2026.11,986 entries · CC-BY 4.0

Construction Manager at Risk (CMAR): How the GMP Works

How construction manager at risk (CMAR, or CM/GC) works: pre-construction services, the GMP, early GMPs and the contract terms owners should define.

Written and maintained by CASRAI Editorial Board

Published

On this page

Short answer

Construction manager at risk (CMAR) is a project delivery method in which the owner hires a construction manager early, during design, to give constructability and pricing advice, and then has that same firm build the project for a Guaranteed Maximum Price (GMP) agreed as the design nears completion. The construction manager is “at risk” because it is accountable for delivering the work within the GMP. In US highway contracting the same method is called CM/GC, construction manager/general contractor.

Definition and scope

Three sources define the method from slightly different angles, and reading them together gives a more complete picture than any one of them.

  • Federal Highway Administration (FHWA). Its Every Day Counts page on CM/GC states that the method “consists of two phases-design and construction.” The contractor “acts as the consultant during the design process and can offer constructability and pricing feedback on design options.” The owner is an active participant during design, and the contractor then has an opportunity to bid on the project based on the completed design and schedule.
  • Federal regulation (23 CFR 635.502). For federal-aid highway projects, a CM/GC project is one delivered under a two-phase contract with a CM/GC contractor. “Preconstruction services” are defined as consulting that gives the contracting agency and its designer information about the impacts of design. The “agreed price” is the price agreed between the CM/GC contractor and the contracting agency.
  • Construction Management Association of America (CMAA) republication of an MBP article. The article “Construction Management at-Risk: Who Is Really at Risk?” by Chris Payne, PE, CCM, describes a construction manager engaged early, typically in design, who is accountable for delivering the project within a GMP and who performs pre-construction services such as value engineering and constructability review. CMAA states that republishing the article is not an endorsement.

The common thread is a single builder who joins the team before the drawings are finished, and a price that is fixed later than it would be in a conventional bid. The federal regulation applies only to federal-aid highway projects; the other two sources describe the method more generally. Outside the federal highway program, an owner’s own procurement rules and contract terms govern how the method is applied.

How it works in practice

Phase one: pre-construction services

During design the construction manager works alongside the owner and the architect or engineer rather than competing against others for a finished set of drawings. The FHWA page describes the contractor as a consultant on constructability and pricing. A sample contract published by Loudoun County, Virginia, shows what that looks like in a public owner’s paper: the construction manager is a member of the project team with the county and the design professional, and during pre-construction develops schedules, cost models and estimates, and value-engineering proposals. That is one county’s contract, offered as an example of the practice rather than a universal template.

The pivot: agreeing the price

In the FHWA description, if the owner, the designer and an independent cost estimator agree that the contractor has submitted a fair price, the owner issues a construction contract. If they do not agree, the owner has a choice about how to proceed. Under 23 CFR 635.504(b)(6), a highway agency that is unwilling or unable to enter into a contract with the CM/GC contractor may, with the Division Administrator’s concurrence, start a new procurement. FHWA approval is needed before advertising if federal-aid funds will pay for construction, and the agency may bar the CM/GC contractor from bidding if that contractor likely has a competitive advantage. Put plainly, the two-phase structure gives the owner a way out if the price cannot be agreed, at least in the federal highway setting.

In the Loudoun County sample, the GMP submittal is made at the point of 100% completion of the construction documents, or a designated portion of them. It includes the construction phase fee, the general conditions cost and allowances. The contract also allows an early GMP for a designated portion of the work, with early GMPs for site work and for long-lead major mechanical and electrical equipment named as examples.

Phase two: construction under the GMP

Once the GMP is accepted the construction manager is accountable for delivering the project within it. The CMAA/MBP article is direct about where the risk then sits. The construction manager absorbs an overrun when the GMP was set before trade buyout or before the design was complete. The owner carries the risk of design changes after the GMP is set, of gaps as the design progresses, and of quality concerns if cost-cutting follows an overrun.

Payment rules on federal-aid highway work

For federal-aid highway CM/GC projects, 23 CFR 635.504(e) states that the cost plus a percentage of cost method, and the percentage of construction cost method, “shall not be used” to pay for either preconstruction or construction services. If compensation is based on actual costs, an approved indirect cost rate must be used. This is a rule for that program, not a statement about how all CMAR contracts are priced.

Contract stages compared

The data table below the main text sets out each stage of a CMAR delivery, what the sources say happens there, and which source states it. Every cell traces to one of the documents listed under Sources. The table is meant as a reading aid: when you open an actual CMAR agreement, it shows which clauses to look for at each stage.

CMAR is often confused with design-build, because in both the builder is involved before construction starts. The difference is who holds the design relationship. In the CMAR descriptions above, the owner keeps its own designer and the construction manager acts as a consultant to that designer and the owner. The CMAA/MBP article notes that two enhancements, design-assist and delegated design, blur the line between designer and builder responsibility, which is one reason the contract language matters. For a side-by-side treatment, see the CASRAI comparison design-build vs design-bid-build, which also answers whether CMAR is the same as design-build.

Where it matters for labs and research facilities

Laboratory buildings carry large mechanical and electrical scopes, which makes the early GMP provision in the Loudoun County sample relevant to them: it names long-lead major mechanical and electrical equipment as work that can be priced and committed ahead of the full GMP. Early involvement of the builder during design also means constructability and pricing feedback arrives while the drawings can still change. Owners planning a laboratory should read this page alongside the CASRAI guides on laboratory construction and research facility design, and the background on the Lean Construction Institute.

The sources read for this page do not address laboratory-specific contract terms, so decisions about biosafety, containment or equipment commissioning belong in the owner’s own contract documents and with its design team.

Common misunderstandings

The CMAA/MBP article identifies three pitfalls that arise because owners and construction managers read the same contract differently. They can be used as a checklist of terms to define before the GMP is signed.

“The GMP is the total project cost”

Owners often treat the GMP as the total cost of the project. The construction manager sees it as a conditional number built on assumptions about the design and scope. The article reports disputes over what was “reasonably inferable” from incomplete documents. Mitigations it lists include tailoring the “reasonably inferable” language, avoiding premature execution of the GMP, and using shared savings provisions.

Contingency confusion

Parties may disagree on who controls contingency and who approves its use. The article recommends defining control, approval rights and drawdown, setting the amount according to how complete the design is, and splitting shared pools at closeout. The Loudoun County sample reflects the same logic: design contingency decreases as the construction documents become more complete, and a construction manager contingency sits inside the GMP.

An elevated standard of care

Because the construction manager reviews the design during pre-construction, courts have occasionally held it to a higher standard of care. The article says case law on this is limited. Its suggested response is to define responsibilities and limit the construction manager’s liability for design issues in the contract.

“At risk” means the owner has no risk

The article’s title asks who is really at risk, and its answer is that both sides are. The construction manager bears overruns when the GMP was set early, and the owner bears post-GMP design changes and gaps in design progression. The method moves risk; it does not remove it.

Frequently asked questions

What does “at risk” mean in construction manager at risk?

It means the construction manager is accountable for delivering the project within the GMP and absorbs overruns inside it. The CMAA/MBP article states the accountability; the contract defines which costs the GMP actually covers.

Is CMAR the same as CM/GC?

The terms describe the same two-phase approach. CM/GC is the term used in the FHWA material and in 23 CFR 635 for highway projects. CMAR is the term used in the CMAA/MBP article and in many building contracts.

What is a Guaranteed Maximum Price?

A GMP is the ceiling price the construction manager commits to for the work, agreed as the design nears completion. According to the CMAA/MBP article it is a conditional number based on stated assumptions, not an unconditional guarantee of final project cost.

Can the owner walk away if the price is not agreed?

On federal-aid highway projects, 23 CFR 635.504(b)(6) allows a highway agency that is unwilling or unable to contract with the CM/GC contractor to start a new procurement, with the Division Administrator’s concurrence. Other owners are governed by their own procurement rules and the terms of the pre-construction agreement.

Can the construction manager bid on the construction phase?

FHWA describes the contractor as having an opportunity to bid on the project based on the completed design and schedule. The federal regulation allows the agency to bar the CM/GC contractor from bidding if it likely has a competitive advantage.

Sources

Data: Construction manager at risk (CMAR) delivery stages and the sources that describe them

Compares the stages of a CMAR / CM/GC delivery (pre-construction services, price agreement, early GMP, construction under the GMP, risk allocation, payment rules) as stated in FHWA guidance, 23 CFR 635, a CMAA-republished MBP article and one county sample contract.

Period covered: 2026. Coverage: United States.

Construction manager at risk (CMAR) delivery stages and the sources that describe them
StageWhat the source statesSourceScope of source
Pre-construction servicesContractor acts as consultant during design and offers constructability and pricing feedback on design optionsFHWA Every Day Counts, CM/GCHighway CM/GC
Pre-construction servicesConsulting that gives the contracting agency and its designer information about the impacts of design23 CFR 635.502Federal-aid highway
Pre-construction servicesConstruction manager develops schedules, cost models and estimates, and value engineering as a member of the project teamLoudoun County sample CM at Risk contract, Part 1One county contract
Price agreementIf owner, designer and independent cost estimator agree the price is fair, owner issues a construction contractFHWA Every Day Counts, CM/GCHighway CM/GC
Price agreementIf the agency is unwilling or unable to contract with the CM/GC contractor it may start a new procurement with Division Administrator concurrence23 CFR 635.504(b)(6)Federal-aid highway
Price agreementGMP submitted at 100% completion of construction documents or a designated portion; includes construction phase fee, general conditions cost and allowancesLoudoun County sample CM at Risk contract, Part 1One county contract
Early GMPEarly GMP may cover site work and long-lead major mechanical and electrical equipmentLoudoun County sample CM at Risk contract, Part 1One county contract
Construction under the GMPConstruction manager is accountable for delivering the project within the GMPCMAA republication of MBP articleGeneral description
Risk allocationConstruction manager absorbs overrun if GMP set before trade buyout or full design; owner bears post-GMP design changes and design-progression gapsCMAA republication of MBP articleGeneral description
Payment methodCost plus a percentage of cost and percentage of construction cost methods shall not be used; actual-cost compensation needs an approved indirect cost rate23 CFR 635.504(e)Federal-aid highway
ContingencyDesign contingency decreases as construction documents become more complete; construction manager contingency sits within the GMPLoudoun County sample CM at Risk contract, Part 1One county contract

Follow CASRAI

Research-administration guidance, standards updates and independent tool reviews.

Ask CASRAI · full access

Ask about Construction Manager at Risk (CMAR): How the GMP Works

Full access: large monthly usage, up to 10 source passages behind each answer, and MCP and API access for Claude Code, Codex and other CLIs. Cancel any time.

An AI assistant for research: funder rules, compliance, methods and publishing. It links the sources behind its answers and labels answers that come from a web search.

Answers draw on CASRAI's guides and dictionary plus the federal and funder documents we index: Federal Register, Grants.gov, Regulations.gov and UKRI.

Works on this site and inside Claude, Cursor and the AI tools you already use.

Everything CASRAI publishes — this page, the dictionary, the guides and the news — stays open to read, with no account and no card.

Referenced across the research world

University of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logoUniversity of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logo
  • University of Cambridge logo
  • Columbia University logo
  • Crossref logo
  • University of Edinburgh logo
  • Harvard University logo
  • University of Oxford logo
  • Princeton University logo
  • Stanford School of Medicine logo
  • University College London logo
  • ORCID logo

View CASRAI adoption →