Written and maintained by CASRAI Editorial Board
Last updated
A goods receipt note (GRN) is the record a receiving party makes when ordered goods arrive: what came, how much, when, and who accepted it. In procurement it is the receiving leg of the purchase order, goods receipt and invoice trio, and a common accounts-payable control holds payment until the three agree. The one field list this page can source to a primary document is the federal receiving report required under FAR 32.905.
Definition and scope
“Goods receipt note” and “goods received note” are common commercial names for a document or system entry that confirms delivery against an order. No standards body defines a universal GRN form for commercial or academic buyers, so the exact fields differ by organization and by purchasing system. The federal acquisition rules do not use the term “GRN” at all. They speak of a receiving report or “other Government documentation authorizing payment” (FAR 32.905(c)), and that is the closest primary-source description of what such a record must contain.
A GRN is not the purchase order, which states what was requested (see purchase requisition vs. purchase order), and it is not the supplier’s invoice, which states what is being billed. It is the buyer’s own evidence about what physically arrived.
How a receiving record is used in practice
Under FAR 32.905(c), payments are to be supported by a receiving report or other documentation authorizing payment (interim cost-reimbursement service payments are excepted). The receiving official is expected to forward that document to the payment office by the 5th working day after Government acceptance or approval, and the forwarding deadline does not extend the payment due date. The receiving report must also refer to the same contract authorization as the invoice, which is why a proper invoice under FAR 32.905(b) lists the contract number or authorization and the order and line item numbers.
FAR 46.401 adds that Government inspection is documented on an inspection or receiving report form, or on a commercial shipping document or packing list where agency procedures allow it. In other words, a packing list can serve as the record only when the buyer’s procedure says so; by itself it is a supplier document.
Many organizations describe the matching of purchase order, goods receipt and invoice before payment as a “three-way match,” a common accounts-payable control. The hospital supply chain guide describes how that reconciliation fits into procurement and inventory management, and the EDI term entry covers the advance ship notice that often precedes a physical delivery.
What a receiving report must show: the federal field list
FAR 32.905(c) sets out the minimum contents of the document that authorizes payment. This is a federal rule, not a universal GRN standard, but it is a useful checklist because every item has a stated purpose.
| FAR 32.905(c) item | What it ties to |
|---|---|
| Contract number or other authorization for supplies delivered or services performed | The same authorization the invoice must cite (32.905(b)) |
| Description of supplies delivered or services performed | What was actually delivered, as opposed to what was ordered |
| Quantities received and accepted, or services performed, if applicable | Quantity accepted, which can differ from quantity shipped |
| Date supplies were delivered or services performed | Delivery date, separate from the acceptance date |
| Date the designated official accepted the supplies or services | The date acceptance occurred, which the 5th-working-day forwarding rule counts from |
| Signature, printed name, title, mailing address and contact details of the responsible official | Who is accountable for the acceptance |
Note the separation of three things a casual receiving note often blurs: when the goods were delivered, when they were accepted, and how many were accepted rather than merely delivered.
Where it matters: acceptance, rejection and timing
The receiving record is also where acceptance and rejection become documented events. Three rules from the federal acquisition regulation show why the timing and wording matter:
- Prompt decisions. The standard inspection clause for fixed-price supplies, FAR 52.246-2(j), says the Government “shall accept or reject supplies as promptly as practicable after delivery,” unless the contract provides otherwise.
- Rejection notices. Under FAR 46.407, notices of rejection must include the reasons and be furnished promptly to the contractor, because delayed notice can allow acceptance to be implied as a matter of law. Under 46.407(g), the notice must be in writing when supplies are rejected at a place other than the contractor’s plant, when the contractor persists in offering nonconforming supplies, or when delivery was late without excusable cause.
- Finality of acceptance. FAR 52.246-2(k) states that acceptance is conclusive except for latent defects, fraud, or gross mistakes amounting to fraud, or as otherwise provided in the contract.
These are federal contract rules, and a purchase on a commercial order is governed by its own terms. The shared lesson is that the receiving entry is the dated evidence of what was accepted and what was refused. Our guide to filing a freight damage or shortage claim covers the carrier side of discrepancies found at the dock, and vendor scorecard metrics covers how receiving discrepancies can feed supplier performance review. For federal awards, federal procurement for research institutions sets the wider decision sequence.
Common misunderstandings
A packing slip is the same as a GRN
A packing list or slip comes from the supplier and says what was shipped. FAR 46.401 allows a packing list to serve as the inspection record only under agency procedures; the receiving party’s own record of what arrived and was accepted is the GRN function.
Signing for a delivery means it has been inspected
Under the FAR structure, delivery, inspection and acceptance are distinct events with their own dates, which is why the receiving report asks for both the delivery date and the acceptance date.
The GRN is only an inventory entry
It also supports payment: in the federal setting, payment is supported by the receiving report, and the report must match the invoice’s contract authorization.
“GRN” is a regulatory term
It is not. The FAR uses “receiving report,” and commercial systems use “goods receipt” or “goods received note” for their own documents.
FAQ
What is a goods receipt note used for?
It records that ordered goods were received and in what quantity, so that the purchase order, delivery and invoice can be reconciled before payment is released.
Is a goods receipt note the same as a receiving report?
They serve the same function. “Receiving report” is the term used in the federal acquisition regulation; “goods receipt note” is the common commercial name.
Who completes it?
Under FAR 32.905(c), the receiving official signs it and includes a printed name, title and contact details. Other organizations assign this by their own procedures.
How quickly must it be forwarded for payment?
In the federal rule, by the 5th working day after Government acceptance or approval, unless other arrangements have been made, and this does not extend payment due dates.
Sources
- FAR 32.905, Payment documentation and process, acquisition.gov/far/32.905 (checked 2026-10-29).
- FAR Subpart 46.4, Government contract quality assurance, acquisition.gov/far/subpart-46.4 (checked 2026-10-29).
- FAR 52.246-2, Inspection of supplies, fixed-price, acquisition.gov/far/52.246-2 (checked 2026-10-29).