US Department of Energy Declines Three Proposed National Interest Electric Transmission Corridors

The US Department of Energy announced it will not designate three proposed National Interest Electric Transmission Corridors under the Federal Power Act.

Published 27 Nov 2026· 7 minute read
High-voltage overhead electric power transmission pole, transformer equipment, and fenced substation perimeter
Photo: Делфина / Wikimedia Commons, CC BY-SA 4.0 (cropped). Source · Licence

The U.S. Department of Energy announced in a Notice of Availability filed on November 27, 2026, that it will not designate three proposed National Interest Electric Transmission Corridors across the Upper Midwest, Southwest, and Great Lakes. The decision halts federal backstop siting pathways and redirected transmission loan eligibility, impacting interregional grid modeling, national laboratory interconnection studies, and university power-systems research initiatives nationwide.

Department of Energy Declines Three Priority Transmission Corridors

The U.S. Department of Energy Office of Electricity formally concluded that there is not a sufficient basis to designate three major National Interest Electric Transmission Corridors (NIETCs). The official report, signed on October 8, 2026, by Catherine Jereza, Assistant Secretary for Electricity, was posted on public inspection ahead of Federal Register publication. The notice concludes the corridor designation process initiated in December 2024, when the department invited public feedback on three proposed interstate transmission routes under 89 FR 101597.

Designation as an electric transmission corridor confers specialized regulatory status upon regions experiencing severe capacity constraints. Designation opens access to dedicated federal financing tools and permits the Federal Energy Regulatory Commission (FERC) to exercise backstop siting authority if state utility commissions deny permits or delay approvals past statutory deadlines. By declining these designations, the department leaves transmission planning, line routing, and right-of-way permitting to state utility commissions, regional transmission organizations, and private developers.

Corridor Profiles and Statutory Siting Criteria

The three declined proposals addressed distinct regional bottlenecks across the North American power grid. Each corridor had been advanced through preliminary screening based on projected transfer constraints between regional interconnections. The Department of Energy evaluated technical performance metrics alongside community feedback before issuing its final negative determination under 16 U.S.C. 824p.

Proposed Corridor Geographic Scope Target Grid Objective Primary Siting and Technical Bottlenecks Federal Program Impact
Tribal Energy Access Corridor North Dakota, South Dakota, Nebraska Interconnecting tribal generation to bulk transmission lines Multi-jurisdictional tribal sovereignty, sovereign rights-of-way, market access Transmission Facilitation Program capacity contracts; tribal loan guarantees
Southwestern Grid Connector Corridor Southeastern Colorado, New Mexico, Oklahoma Panhandle High-voltage direct current (HVDC) transfer between Eastern and Western Interconnections Landowner opposition, private property rights, agricultural eminent domain concerns Inflation Reduction Act Section 50151 direct transmission facility loans
Lake Erie-Canada Corridor Northern Pennsylvania, Lake Erie, Ontario Intertie Bi-directional cross-border transfer with Canadian system operators Submerged freshwater cable engineering, international treaty reviews, merchant risk Federal backstop siting under Section 216(b); cross-border presidential permits

The Tribal Energy Access proposal sought to connect renewable generation across sovereign reservations—including Standing Rock, Cheyenne River, Rosebud, and Pine Ridge—to regional transmission lines. The Southwestern Grid Connector aimed to bridge the persistent physical seam between the Western and Eastern Interconnections across Colorado and New Mexico, while the Lake Erie-Canada project evaluated underwater direct current cables to Ontario to exchange seasonal balancing reserves.

Regulatory Background: Section 216 and the 2023 Needs Study

The authority to designate National Interest Electric Transmission Corridors was established under Section 1221 of the Energy Policy Act of 2005, creating Section 216 of the Federal Power Act. Congress overhauled the statute through the Infrastructure Investment and Jobs Act (IIJA) of 2021, expanding statutory criteria to encompass expected future transmission constraints driven by changing generation portfolios, extreme weather vulnerabilities, and rising industrial power demand.

In October 2023, the department published its comprehensive National Transmission Needs Study, produced with national laboratory modeling teams. That report found that interregional transfer capacity must grow substantially across regional seams to safeguard reliability and mitigate localized price volatility. To operationalize these findings, the Grid Deployment Office established a multi-phase NIETC designation process, structuring early stakeholder engagement before initiating environmental reviews under the National Environmental Policy Act.

Long-term power market projections in the EIA Annual Energy Outlook show that regional transmission constraints directly influence wholesale power prices and industrial expansion. While the amended statute sought narrower, project-specific corridors to avoid court reversals that invalidated early 2007 designations, the framework still faced persistent friction over federal preemption of state siting authority.

Stakeholder Pushback, Eminent Domain Concerns, and Policy Shifts

The decision to reject the three designations reflects strong regional pushback and a realignment of federal energy doctrine. During the public comment period, agricultural landowners, rural electric cooperatives, and local county commissions registered vehement objections, especially in the footprint of the Southwestern Grid Connector. Opponents warned that corridor designation would facilitate federal eminent domain under FERC backstop permitting, bypassing state commissions and encroaching on private land rights.

The formal notice explicitly aligns the department’s determination with recent executive directives, including Executive Order 14154, “Unleashing American Energy,” and Executive Order 14262, “Strengthening the Reliability and Security of the United States Electric Grid,” alongside Energy Secretary Chris Wright’s February 2025 Secretarial Order on domestic energy dominance. These policies emphasize advancing energy infrastructure without imposing federal preemption mechanisms that provoke protracted litigation or infringe on local prerogatives.

Conversely, clean energy developers and tribal consortia expressed disappointment with the withdrawal. Groups such as the Oceti Sakowin Power Authority viewed the Tribal Energy Access designation as essential for overcoming grid bottlenecks that isolate tribal reservations from wholesale electricity markets. Analysts noted that without federal corridor designations, major interregional lines remain vulnerable to state-by-state approval processes where a single state refusal can stall a multi-state project.

Implications for Power Systems Research, Grid Modeling, and Lab Grants

The withdrawal of these proposed corridors carries immediate technical implications for academic power-systems researchers, research administrators, and national laboratory teams. Electrical engineering faculties modeling bulk power flows and dynamic market clearing using software such as PowerWorld Simulator must adjust simulation parameters. Rather than assuming federally expedited interregional corridors, researchers must calibrate expansion models to reflect state permitting timelines, localized merchant line risks, and grid-enhancing technologies on existing rights-of-way.

At the national laboratories—including the National Renewable Energy Laboratory (NREL), Pacific Northwest National Laboratory (PNNL), and Argonne National Laboratory—teams updating national grid capacity models and the EIA Energy Atlas must revise geospatial routing layers. Future interregional capacity scenarios can no longer incorporate presumed federal corridors in Colorado, New Mexico, or the Upper Plains as base-case assumptions, altering regional contingency analyses.

The technical shift also underscores the growing importance of operational technology security in power systems research. As grid operators turn to dynamic line rating, automated switching, and grid-enhancing technologies within existing rights-of-way, research offices must align cyber-physical projects with federal AI power grid OT security guidelines to protect substation automation from emerging threats.

For university research offices managing interdisciplinary grid innovation consortia, the regulatory shift highlights the distinct compliance environments governing federal energy research. Faculty seeking transmission research awards must navigate administrative requirements that separate Department of Energy grants from other basic science awards, as detailed in comparisons of NSF vs. DOE grant requirements. Multi-institution proposals targeting transmission reliability must now prioritize existing right-of-way optimization, advanced conductor deployment, and state-coordinated planning frameworks.

Future Federal Transmission Financing and State-Led Approvals

The Department of Energy’s decision takes effect upon publication in the Federal Register on November 30, 2026. Developers of planned transmission lines across the Upper Midwest, the Southwest seam, and the Lake Erie basin must now advance their projects through standard state utility commission dockets, regional transmission organization queues, and conventional federal rights-of-way reviews.

Financially, projects within these corridors cannot access designation-dependent federal financing. Section 50151 of the Inflation Reduction Act provided $2 billion in loan authority restricted to projects located within designated NIETCs. While developers may still seek support through the broader $2.5 billion Transmission Facilitation Program or Title 17 clean energy financing loan programs, they will not receive the statutory prioritization reserved for designated national corridors.

The department emphasized that declining these three proposals does not terminate its statutory authority under Section 216 of the Federal Power Act. The Grid Deployment Office will continue monitoring transmission congestion, evaluating triennial transmission needs studies, and reviewing future corridor applications. However, the decision establishes a high evidentiary bar, signaling that federal authorities will not intervene in interstate transmission siting without demonstrated local consensus and compelling, unresolvable reliability imperatives.

Sources

Ask CASRAI · full access

Ask about this story

Full access: large monthly usage, up to 10 source passages behind each answer, and MCP and API access for Claude Code, Codex and other CLIs. Cancel any time.

An AI assistant for research: funder rules, compliance, methods and publishing. It links the sources behind its answers and labels answers that come from a web search.

Answers draw on CASRAI's guides and dictionary plus the federal and funder documents we index: Federal Register, Grants.gov, Regulations.gov and UKRI.

Works on this site and inside Claude, Cursor and the AI tools you already use.

Everything CASRAI publishes — this page, the dictionary, the guides and the news — stays open to read, with no account and no card.

Referenced across the research world

University of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logoUniversity of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logo
  • University of Cambridge logo
  • Columbia University logo
  • Crossref logo
  • University of Edinburgh logo
  • Harvard University logo
  • University of Oxford logo
  • Princeton University logo
  • Stanford School of Medicine logo
  • University College London logo
  • ORCID logo

View CASRAI adoption →