FERC Releases Environmental Assessment for Starks Hydroelectric Project Surrender and Dam Removal

FERC released an Environmental Assessment for the surrender and dam removal of the Starks Hydroelectric Project on Maine’s Lemon Stream.

Published 28 Nov 2026· 6 minute read
Low-head concrete river dam and impoundment spillway prior to dam removal and stream restoration
Photo: U. S. Fish and Wildlife Service – Northeast Region / Wikimedia Commons, Public domain (cropped). Source

On November 27, 2026, the Federal Energy Regulatory Commission released an Environmental Assessment for the Starks Hydroelectric Project approving the surrender of license exemption and complete dam removal on Lemon Stream in Somerset County, Maine, establishing an unencumbered fluvial research corridor for university ecologists studying Atlantic salmon habitat recovery and sediment dynamics.

Surrender Application and Environmental Assessment Findings

The Federal Energy Regulatory Commission (FERC) Office of Energy Projects formally published its Notice of Availability of the staff-prepared Environmental Assessment (EA) under Document No. 2026-24101 (Project No. 8791-005) pursuant to regulations codified at 18 CFR Part 380. Commission staff evaluated the decommissioning application filed by project exemptee R.J. Fortier Hydropower, Inc., who requested authorization to surrender the project exemption and dismantle all generation and water-impounding infrastructure. The environmental review, conducted under identification number EAXX-019-20-000-1781511078, concluded that the proposed surrender and physical removal, when executed alongside mandatory environmental protective measures, will not constitute a major federal action significantly affecting the quality of the human environment.

The environmental review process adhered to established standards administered across federal agencies under the U.S. Environmental Protection Agency NEPA review framework, analyzing environmental baseline conditions, project alternatives, water quality impacts, and migratory aquatic species passage. Decommissioning represents an operational transition away from aging, low-capacity run-of-river infrastructure toward stream naturalization, mirroring national initiatives cataloged in research platforms such as HydroSource that track hydropower lifecycle assessments and asset retirements.

Decommissioning Specifications and Regulatory Framework

The Starks Hydroelectric Project operated under an exemption for small conduit and small hydroelectric power projects of 10 megawatts or less, governed by 18 CFR Part 4 Subpart K under statutory provisions of the Federal Power Act codified at 16 U.S.C. Chapter 12 Subchapter I. The surrender application encompasses the total deconstruction and removal of the concrete dam spillway, timber flashboards, powerhouse generating units, intake structures, and electrical interconnection equipment situated across Lemon Stream. The project occupies private riparian parcels without encumbering federal lands.

Deconstruction protocols outlined in the EA emphasize controlled reservoir drawdown, gradual notch excavation, and containment of accumulated alluvial sediments to prevent downstream turbidity spikes. Commission staff integrated environmental measures requiring staged dewatering, fish rescue salvage operations, continuous dissolved oxygen monitoring, and bank revegetation with native riparian seed mixes.

Project Metric / Regulatory Element Specification and Staff Determination
Project Identification Starks Hydroelectric Project, FERC Docket No. P-8791-005
Federal Notice Publication FR Doc. 2026-24101 (Published November 27, 2026)
Exemptee / Applicant R.J. Fortier Hydropower, Inc.
Waterway Location Lemon Stream, Somerset County, Maine (Sandy River Subbasin)
Federal Land Status No federal lands occupied
Regulatory Action Surrender of small hydro exemption and complete decommissioning
NEPA Determination Finding of No Significant Impact (FONSI) with protective measures
Public Comment Deadline December 23, 2026 (5:00 p.m. Eastern Time)

Ecological Context and Diadromous Fish Migration in the Kennebec Basin

Lemon Stream represents an ecologically critical tributary of the Sandy River within Maine’s Kennebec River watershed, an area prioritized by state and federal biologists for native diadromous fish restoration. Low-head dams alter natural stream morphology by converting free-flowing lotic environments into slow-moving lentic impoundments, trapping coarse gravels, elevating summer water temperatures, and creating insurmountable physical barriers to upstream fish passage.

The removal of the Starks dam directly benefits the Gulf of Maine Distinct Population Segment of anadromous Atlantic salmon (Salmo salar), a federally endangered population that depends on unobstructed access to cold, gravel-bedded headwater streams for spawning redd construction and juvenile rearing. Reconnecting Lemon Stream to the Sandy River also restores longitudinal migration corridors for alewife, blueback herring, and catadromous American eel. Recent aquatic studies featured in PLOS Water demonstrate that tributary dam removals produce rapid reductions in thermal stress and restore natural flow pulses essential for native salmonid survival.

Stakeholder Positions and Resource Agency Coordination

The decommissioning plan reflects extensive multi-agency coordination among FERC, the U.S. Fish and Wildlife Service, the National Oceanic and Atmospheric Administration (NOAA Fisheries), the Maine Department of Marine Resources, and the Maine Department of Environmental Protection. State resource agencies highlighted that the economic costs of retrofitting modern upstream and downstream fish passage facilities at the small Starks facility significantly outweighed the commercial value of its modest power generation.

Regional river conservation coalitions and watershed councils have endorsed full dam removal as the preferred environmental alternative, pointing to previous landmark removals in the Kennebec and Penobscot basins that generated dramatic recoveries in migratory biomass. Clean Water Act Section 401 water quality certifications issued for the surrender require stringent sediment transport safeguards during channel re-exposure.

Implications for River Restoration Research and University Field Stations

The Starks dam removal provides university freshwater ecologists, geomorphologists, and environmental engineering departments with an exceptional natural laboratory to investigate rapid channel re-equilibration. Academic researchers tracking dam removal responses frequently examine bedload sediment transport rates, macroinvertebrate index of biological integrity (IBI) metrics, and environmental DNA (eDNA) detection of returning anadromous fish.

Field investigations conducted across Maine river systems yield crucial longitudinal data sets, frequently disseminated in scholarly venues such as the Environmental Monitoring and Assessment Journal. Research teams can integrate findings from Lemon Stream into broader ecological monitoring frameworks modeled after the NSF Long-Term Ecological Research network, advancing empirical predictive models of watershed recovery, gravel bar formation, and benthic recolonization rates following the retirement of obsolete run-of-river dams.

Public Comment Deadlines and Procedural Milestones

FERC established a public comment period closing on December 23, 2026, at 5:00 p.m. Eastern Time. The Commission strongly encourages electronic submissions through its online eFiling portal or via the streamlined eComment system, which accepts unindexed comments up to 6,000 characters without prior user registration. Stakeholders opting for paper submissions must deliver filings addressed to Secretary Debbie-Anne A. Reese at FERC headquarters in Washington, D.C., referencing docket number P-8791-005 on the cover page.

Inquiries regarding administrative intervention, technical rehearing procedures, or public participation may be directed to the FERC Office of Public Participation or project coordinator Diana Shannon in the Office of Energy Projects. Following the close of the comment window, Commission staff will review public submissions before drafting a final surrender order that specifies the timeline for on-site structural deconstruction and post-removal site stabilization.

Sources

Ask CASRAI · full access

Ask about this story

Full access: large monthly usage, up to 10 source passages behind each answer, and MCP and API access for Claude Code, Codex and other CLIs. Cancel any time.

An AI assistant for research: funder rules, compliance, methods and publishing. It links the sources behind its answers and labels answers that come from a web search.

Answers draw on CASRAI's guides and dictionary plus the federal and funder documents we index: Federal Register, Grants.gov, Regulations.gov and UKRI.

Works on this site and inside Claude, Cursor and the AI tools you already use.

Everything CASRAI publishes — this page, the dictionary, the guides and the news — stays open to read, with no account and no card.

Referenced across the research world

University of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logoUniversity of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logo
  • University of Cambridge logo
  • Columbia University logo
  • Crossref logo
  • University of Edinburgh logo
  • Harvard University logo
  • University of Oxford logo
  • Princeton University logo
  • Stanford School of Medicine logo
  • University College London logo
  • ORCID logo

View CASRAI adoption →