FERC Sets Environmental Assessment Schedule for Southern Star Evergy McNew Pipeline Project

FERC set the environmental assessment schedule for Southern Star’s pipeline expansion to fuel Evergy’s planned McNew Power Plant in Reno County, Kansas.

Published 28 Nov 2026· 7 minute read
Piping, heat recovery steam generators, and exhaust stacks at a natural gas combined-cycle power plant
Photo: Harald the Bard / Wikimedia Commons, CC BY-SA 4.0 (cropped). Source · Licence

On November 24, 2026, the Federal Energy Regulatory Commission published a formal procedural schedule in the Federal Register setting June 7, 2027, for its environmental assessment of Southern Star Central Gas Pipeline’s Evergy McNew Delivery Project in Reno County, Kansas. The proceeding establishes binding federal milestones, providing energy systems researchers and institutional infrastructure planners critical benchmark data for pipeline reliability modeling and interagency permitting.

Procedural Schedule and Commission Authorization Framework

The Federal Energy Regulatory Commission (FERC) notice, designated as Docket No. CP26-572-000 and documented under Federal Register Document No. 2026-23894 (91 FR 75850), establishes the formal timeline under the National Environmental Policy Act (NEPA) for Southern Star Central Gas Pipeline, Inc. (Southern Star). Southern Star submitted its formal application on August 31, 2026, requesting a Certificate of Public Convenience and Necessity pursuant to Section 7(c) of the Natural Gas Act (15 U.S.C. 717f(c)). The Commission subsequently issued its formal Notice of Application on September 15, 2026, initiating federal coordination for the interstate pipeline infrastructure.

Under the Commission’s procedural framework governed by 18 CFR Part 157, the notice identifies Commission staff’s intent to prepare an Environmental Assessment (EA) for the project. Commission staff assigned the proceeding NEPA tracking identification number EAXX-019-20-000-1788525221. The published schedule fixes June 7, 2027, for the public release of the staff EA, which will open an immediate 30-day public comment period for agency and stakeholder review.

Crucially for interagency permitting coordination, the notice establishes a binding 90-day Federal Authorization Decision Deadline of September 5, 2027, under 18 CFR 157.22(a). This regulatory provision mandates that all other federal agencies, as well as state agencies administering federally delegated programs, must reach a final decision on required authorizations within 90 days following issuance of the staff environmental document, unless another schedule is mandated by federal law.

Technical Specifications and Facility Engineering

The Evergy McNew Power Plant Delivery Project comprises targeted pipeline, compression, and metering infrastructure across three Kansas counties: Reno, Harvey, and Stafford. The primary objective is to deliver up to 123,000 million cubic feet per day (MMcf/d) of firm natural gas transportation service from Southern Star’s established mainline system to Evergy Kansas Central, Inc.’s planned McNew Power Plant in Reno County. According to local reporting by the Hutch Post, the new $1 billion combined-cycle generating station represents one of the largest infrastructure investments in Reno County history, designed to generate 705 to 765 megawatts (MW) of electricity to support regional grid reliability.

The physical facilities defined in Southern Star’s certificate filing include:

  • Line RE Lateral Pipeline: Construction of a new 1.6-mile-long, 30-inch-diameter natural gas transmission lateral connecting a new compressor station to the power plant delivery point in Reno County.
  • Hutchinson Compressor Station: Construction and operation of a new greenfield compressor facility along Southern Star’s existing 26-inch-diameter Hugoton Loop Line RA in Reno County.
  • Evergy Meter Station: Construction of a new measurement and flow control station at the McNew plant site.
  • Compressor Station Modifications: Piping and mechanical adjustments within existing facilities at the Hesston Compressor Station in Harvey County and the Stafford Compressor Station in Stafford County.
  • In-Line Inspection Infrastructure: Installation of a pig launcher and tie-in piping at the mainline connection, along with a pig receiver at the Evergy Meter Station for pipeline integrity management.

The table below summarizes the core parameters, facility components, and regulatory milestones for Docket No. CP26-572-000:

Parameter or Milestone Specification or Target Date Regulatory Citation or Authority
Docket Number Docket No. CP26-572-000 Federal Energy Regulatory Commission
Lead Applicant Southern Star Central Gas Pipeline, Inc. Natural Gas Act Section 7(c)
Firm Transportation Capacity Up to 123,000 MMcf/d 18 CFR Part 157 Application
New Lateral (Line RE) 1.6 miles, 30-inch diameter Reno County, Kansas
New Greenfield Compression Hutchinson Compressor Station Hugoton Loop Line RA (Reno County)
Station Modifications Hesston (Harvey Co.) and Stafford (Stafford Co.) Existing Facility Enhancements
NEPA Tracking Identifier EAXX-019-20-000-1788525221 18 CFR Part 380 Regulations
Environmental Assessment Issuance June 7, 2027 FERC Notice of Schedule (91 FR 75850)
Public Comment Period 30 Days Post-Issuance FERC Procedural Rules
Federal Decision Deadline September 5, 2027 18 CFR 157.22(a) Binding Mandate

NEPA Scoping History and Environmental Reviews

The Commission’s procedural schedule emerges from an environmental scoping process initiated in autumn 2026 pursuant to 18 CFR Part 380, which governs FERC’s NEPA implementation. On October 1, 2026, the Commission issued a Notice of Scoping Period Requesting Comments on Environmental Issues to affected landowners, government agencies, elected officials, Native American tribes, and public interest groups. In Footnote 1 of the schedule notice, Secretary Debbie-Anne A. Reese clarified that the McNew Power Plant is a proposed new combined-cycle turbine generating facility rather than an earlier mischaracterized conversion of an existing facility.

During scoping, the U.S. Army Corps of Engineers (USACE) Kansas City District submitted comments noting that if project activities involve dredge or fill in jurisdictional waters of the United States, a Department of the Army permit under Section 404 of the Clean Water Act may be required.

Substantive comments were also filed by local residents. Jared and Yolanda Oatney, represented by counsel Diana Stanley, raised concerns regarding pipeline routing, local geology, operational impacts on a nearby airfield, and protection of special-status species and designated critical habitat. Resident Alexia S. Welch filed comments focusing on groundwater resource protection, geological hazards, air quality and noise emissions, emergency response preparedness, land use considerations, and the cumulative environmental effects of ongoing industrial development in the surrounding basin.

Implications for Energy Researchers, Utilities, and Compliance Offices

For academic energy researchers and utility planners, the Evergy McNew pipeline expansion highlights fundamental dynamics in regional power market design. As regional transmission operators integrate variable renewable generation, high-efficiency combined-cycle natural gas units serve vital balancing roles. Evaluating gas-electric infrastructure coordination requires modeling firm fuel delivery contracts alongside transmission dispatch constraints.

Energy economists tracking pipeline deliverability and regional balancing frequently use data from the EIA natural gas storage report to evaluate how localized pipeline expansions affect storage withdrawal patterns and seasonal hub pricing across the Midcontinent market. High-pressure delivery laterals provide essential empirical parameters for modeling pipeline linepack and transient pressures during peak winter electrical demand.

At the facility level, thermal and mechanical design choices align with broader industrial efficiency standards. Large-scale facilities increasingly reference ASHRAE Standard 90.1 principles when assessing administrative building envelopes and auxiliary energy usage. Additionally, major equipment procurement touches global supply chains, where research administrators analyze international equipment sourcing under Trade Agreements Act compliance rules and Foreign-Trade Zone customs procedures for specialized turbines and compression hardware.

Project Milestones and Upcoming Permitting Deadlines

The publication of Document No. 2026-23894 establishes the timeline leading toward environmental clearance and subsequent Commission action. FERC staff will evaluate scoping input and prepare the environmental assessment in consultation with state and federal cooperating agencies.

The key procedural milestones are established as follows:

  1. June 7, 2027: FERC staff issues the Environmental Assessment for Docket No. CP26-572-000.
  2. June to July 2027: A 30-day public comment period follows EA issuance for stakeholder submissions.
  3. September 5, 2027: The 90-day Federal Authorization Decision Deadline expires under 18 CFR 157.22(a).
  4. Late 2027: The Commission issues a final decision on Southern Star’s Section 7(c) certificate application.
  5. 2028 to 2029: Pending approvals, facility construction and tie-in integration proceed.
  6. Late 2029 to 2030: Target commercial operation for Evergy’s McNew Power Plant.

Sources

Ask CASRAI · full access

Ask about this story

Full access: large monthly usage, up to 10 source passages behind each answer, and MCP and API access for Claude Code, Codex and other CLIs. Cancel any time.

An AI assistant for research: funder rules, compliance, methods and publishing. It links the sources behind its answers and labels answers that come from a web search.

Answers draw on CASRAI's guides and dictionary plus the federal and funder documents we index: Federal Register, Grants.gov, Regulations.gov and UKRI.

Works on this site and inside Claude, Cursor and the AI tools you already use.

Everything CASRAI publishes — this page, the dictionary, the guides and the news — stays open to read, with no account and no card.

Referenced across the research world

University of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logoUniversity of Cambridge logoColumbia University logoCrossref logoUniversity of Edinburgh logoHarvard University logoUniversity of Oxford logoPrinceton University logoStanford School of Medicine logoUniversity College London logoORCID logo
  • University of Cambridge logo
  • Columbia University logo
  • Crossref logo
  • University of Edinburgh logo
  • Harvard University logo
  • University of Oxford logo
  • Princeton University logo
  • Stanford School of Medicine logo
  • University College London logo
  • ORCID logo

View CASRAI adoption →